# ColaFlow Days 7-10 Roadmap
|
||||
|
||||
**Date**: 2025-11-03
|
||||
**Prepared By**: Product Manager Agent
|
||||
**Sprint**: M1 Sprint 2 - Enterprise-Grade Multi-Tenancy & SSO
|
||||
**Status**: Planning Complete
|
||||
|
||||
---
|
||||
|
||||
## Overview
|
||||
|
||||
This roadmap outlines Days 7-10 of the 10-day sprint, building on the foundation established in Days 1-6 (Authentication, RBAC, Role Management).
|
||||
|
||||
**Strategic Goal**: Complete M1.1 core features and prepare for M2 MCP integration.
|
||||
|
||||
---
|
||||
|
||||
## Day 7: Email Service + Verification + Password Reset
|
||||
|
||||
**Duration**: 8 hours
|
||||
**Priority**: P1 (High - Security and UX)
|
||||
**Dependencies**: None (independent feature)
|
||||
|
||||
### Objectives
|
||||
|
||||
1. Integrate email service (SendGrid or SMTP)
|
||||
2. Implement email verification flow
|
||||
3. Implement password reset flow
|
||||
4. Create email templates
|
||||
5. Add rate limiting for security
|
||||
|
||||
### Deliverables
|
||||
|
||||
**Backend**:
|
||||
- Email service abstraction (`IEmailService`)
|
||||
- SendGrid implementation (primary)
|
||||
- SMTP fallback implementation
|
||||
- Email verification tokens (24-hour expiration)
|
||||
- Password reset tokens (1-hour expiration)
|
||||
- Rate limiting (max 5 verification emails/hour, max 3 reset emails/hour)
|
||||
|
||||
**API Endpoints**:
|
||||
1. `POST /api/auth/verify-email` - Verify email with token
|
||||
2. `POST /api/auth/resend-verification` - Resend verification email
|
||||
3. `POST /api/auth/forgot-password` - Request password reset
|
||||
4. `POST /api/auth/reset-password` - Reset password with token
|
||||
|
||||
**Database**:
|
||||
- Add `email_verified` column to `identity.users`
|
||||
- Add `email_verified_at` column
|
||||
- Create `email_verification_tokens` table
|
||||
- Create `password_reset_tokens` table
|
||||
|
||||
**Email Templates**:
|
||||
- Welcome + verification email
|
||||
- Password reset email
|
||||
- Password changed confirmation email
|
||||
|
||||
**Tests**:
|
||||
- 20+ integration tests
|
||||
- Email delivery verification (use test inbox)
|
||||
- Token expiration tests
|
||||
- Rate limiting tests
|
||||
|
||||
### Success Criteria
|
||||
|
||||
- ✅ Emails sent successfully (99% delivery rate)
|
||||
- ✅ Verification flow completes in < 30 seconds
|
||||
- ✅ Password reset flow completes in < 30 seconds
|
||||
- ✅ Rate limiting prevents abuse
|
||||
- ✅ 100% test coverage
|
||||
|
||||
---
|
||||
|
||||
## Day 8: Project-Level Roles + Audit Logging
|
||||
|
||||
**Duration**: 8 hours
|
||||
**Priority**: P0 (Critical - Required for M1 Projects module)
|
||||
**Dependencies**: Day 6 (Role Management API)
|
||||
|
||||
### Objectives
|
||||
|
||||
1. Design and implement project-level role system
|
||||
2. Implement role inheritance logic
|
||||
3. Create authorization policies for project operations
|
||||
4. Implement comprehensive audit logging
|
||||
5. Prepare for M1.1 Projects CRUD
|
||||
|
||||
### Deliverables
|
||||
|
||||
**Domain Layer**:
|
||||
- `ProjectRole` enum (ProjectOwner, ProjectManager, ProjectMember, ProjectGuest)
|
||||
- `UserProjectRole` entity
|
||||
- `IUserProjectRoleRepository` interface
|
||||
- Role inheritance rules:
|
||||
- TenantOwner → ProjectOwner (all projects)
|
||||
- TenantAdmin → ProjectManager (all projects)
|
||||
- Project-specific roles override tenant defaults
|
||||
|
||||
**Database**:
|
||||
```sql
|
||||
CREATE TABLE projects.user_project_roles (
|
||||
id UUID PRIMARY KEY,
|
||||
user_id UUID NOT NULL,
|
||||
project_id UUID NOT NULL,
|
||||
role VARCHAR(50) NOT NULL,
|
||||
assigned_at TIMESTAMP NOT NULL,
|
||||
assigned_by_user_id UUID NULL,
|
||||
UNIQUE(user_id, project_id)
|
||||
);
|
||||
```
|
||||
|
||||
**Authorization Policies**:
|
||||
- `RequireProjectOwner` - Full control over project
|
||||
- `RequireProjectManager` - Manage tasks and team
|
||||
- `RequireProjectMember` - Create and update tasks
|
||||
- `RequireProjectAccess` - Read-only access
|
||||
|
||||
**Audit Logging**:
|
||||
```sql
|
||||
CREATE TABLE audit.audit_logs (
|
||||
id UUID PRIMARY KEY,
|
||||
tenant_id UUID NOT NULL,
|
||||
user_id UUID NOT NULL,
|
||||
action VARCHAR(100) NOT NULL,
|
||||
entity_type VARCHAR(50) NOT NULL,
|
||||
entity_id UUID NULL,
|
||||
old_value JSONB NULL,
|
||||
new_value JSONB NULL,
|
||||
ip_address VARCHAR(50) NULL,
|
||||
user_agent VARCHAR(500) NULL,
|
||||
timestamp TIMESTAMP NOT NULL DEFAULT NOW()
|
||||
);
|
||||
```
|
||||
|
||||
**API Endpoints**:
|
||||
1. `POST /api/projects/{projectId}/members` - Add member to project
|
||||
2. `PUT /api/projects/{projectId}/members/{userId}/role` - Update member role
|
||||
3. `DELETE /api/projects/{projectId}/members/{userId}` - Remove member
|
||||
4. `GET /api/projects/{projectId}/members` - List project members
|
||||
5. `GET /api/audit/logs` - Query audit logs (TenantOwner only)
|
||||
|
||||
**Tests**:
|
||||
- 25+ integration tests
|
||||
- Role inheritance tests
|
||||
- Authorization policy tests
|
||||
- Audit log verification
|
||||
|
||||
### Success Criteria
|
||||
|
||||
- ✅ Role inheritance works correctly
|
||||
- ✅ All API operations logged
|
||||
- ✅ Authorization policies enforce project-level permissions
|
||||
- ✅ 100% test coverage
|
||||
|
||||
---
|
||||
|
||||
## Day 9: M1 Core Projects Module - Multi-Tenant Update
|
||||
|
||||
**Duration**: 8 hours
|
||||
**Priority**: P0 (Critical - M1.1 core feature)
|
||||
**Dependencies**: Day 8 (Project-level roles)
|
||||
|
||||
### Objectives
|
||||
|
||||
1. Update existing Projects module for multi-tenancy
|
||||
2. Add project-level authorization
|
||||
3. Integrate project roles
|
||||
4. Complete Epics, Stories, Tasks multi-tenant update
|
||||
5. Test full workflow (register → create project → manage tasks)
|
||||
|
||||
### Deliverables
|
||||
|
||||
**Database Migration**:
|
||||
- Add `tenant_id` column to `projects.projects`
|
||||
- Add `tenant_id` column to `projects.epics`
|
||||
- Add `tenant_id` column to `projects.stories`
|
||||
- Add `tenant_id` column to `projects.tasks`
|
||||
- Update foreign keys
|
||||
- Add EF Core global query filters
|
||||
|
||||
**Application Layer Updates**:
|
||||
- Update all commands to include tenant context
|
||||
- Add project role validation
|
||||
- Update queries to filter by tenant
|
||||
|
||||
**API Updates**:
|
||||
- Protect all endpoints with project-level authorization
|
||||
- Example: `[Authorize(Policy = "RequireProjectMember")]`
|
||||
- Add tenant validation middleware
|
||||
|
||||
**Tests**:
|
||||
- 30+ integration tests
|
||||
- Cross-tenant isolation tests
|
||||
- Project role authorization tests
|
||||
- Full workflow tests (E2E)
|
||||
|
||||
### Success Criteria
|
||||
|
||||
- ✅ All Projects/Epics/Stories/Tasks isolated by tenant
|
||||
- ✅ Project-level authorization works
|
||||
- ✅ No cross-tenant data leakage
|
||||
- ✅ 100% test coverage
|
||||
- ✅ Full E2E workflow passes
|
||||
|
||||
---
|
||||
|
||||
## Day 10: Kanban Workflow + Sprint Management
|
||||
|
||||
**Duration**: 8 hours
|
||||
**Priority**: P1 (High - M1.1 core feature)
|
||||
**Dependencies**: Day 9 (Projects module updated)
|
||||
|
||||
### Objectives
|
||||
|
||||
1. Implement Sprint management
|
||||
2. Enhance Kanban board with sprint support
|
||||
3. Add sprint burndown chart data
|
||||
4. Implement sprint velocity tracking
|
||||
5. Complete M1.1 core features
|
||||
|
||||
### Deliverables
|
||||
|
||||
**Domain Layer**:
|
||||
- `Sprint` entity
|
||||
- `SprintId` value object
|
||||
- Sprint status (Planning, Active, Completed)
|
||||
- Sprint business rules (start/end dates, task capacity)
|
||||
|
||||
**Database**:
|
||||
```sql
|
||||
CREATE TABLE projects.sprints (
|
||||
id UUID PRIMARY KEY,
|
||||
project_id UUID NOT NULL,
|
||||
tenant_id UUID NOT NULL,
|
||||
name VARCHAR(100) NOT NULL,
|
||||
goal TEXT NULL,
|
||||
start_date DATE NOT NULL,
|
||||
end_date DATE NOT NULL,
|
||||
status VARCHAR(20) NOT NULL,
|
||||
created_at TIMESTAMP NOT NULL,
|
||||
FOREIGN KEY (project_id) REFERENCES projects.projects(id)
|
||||
);
|
||||
|
||||
ALTER TABLE projects.tasks
|
||||
ADD COLUMN sprint_id UUID NULL,
|
||||
ADD CONSTRAINT fk_tasks_sprints FOREIGN KEY (sprint_id) REFERENCES projects.sprints(id);
|
||||
```
|
||||
|
||||
**API Endpoints**:
|
||||
1. `POST /api/projects/{projectId}/sprints` - Create sprint
|
||||
2. `PUT /api/projects/{projectId}/sprints/{sprintId}` - Update sprint
|
||||
3. `DELETE /api/projects/{projectId}/sprints/{sprintId}` - Delete sprint
|
||||
4. `POST /api/projects/{projectId}/sprints/{sprintId}/start` - Start sprint
|
||||
5. `POST /api/projects/{projectId}/sprints/{sprintId}/complete` - Complete sprint
|
||||
6. `GET /api/projects/{projectId}/sprints` - List sprints
|
||||
7. `GET /api/projects/{projectId}/sprints/{sprintId}/burndown` - Burndown data
|
||||
8. `POST /api/projects/{projectId}/tasks/{taskId}/assign-to-sprint` - Add task to sprint
|
||||
|
||||
**Analytics**:
|
||||
- Sprint burndown chart data (remaining story points per day)
|
||||
- Sprint velocity (completed story points per sprint)
|
||||
- Sprint completion percentage
|
||||
- Team capacity utilization
|
||||
|
||||
**Tests**:
|
||||
- 20+ integration tests
|
||||
- Sprint workflow tests
|
||||
- Burndown calculation tests
|
||||
- Velocity tracking tests
|
||||
|
||||
### Success Criteria
|
||||
|
||||
- ✅ Full sprint lifecycle works (create → start → complete)
|
||||
- ✅ Tasks can be assigned to sprints
|
||||
- ✅ Burndown chart data accurate
|
||||
- ✅ Velocity tracking functional
|
||||
- ✅ 100% test coverage
|
||||
- ✅ **M1.1 COMPLETE**
|
||||
|
||||
---
|
||||
|
||||
## Summary Timeline
|
||||
|
||||
| Day | Feature | Priority | Hours | Dependencies | Risk |
|
||||
|-----|---------|----------|-------|--------------|------|
|
||||
| **6** | Role Management API | P0 | 6-8 | Day 5 RBAC | LOW |
|
||||
| **7** | Email Service + Verification + Password Reset | P1 | 8 | None | MEDIUM |
|
||||
| **8** | Project-Level Roles + Audit Logging | P0 | 8 | Day 6 | MEDIUM |
|
||||
| **9** | Projects Multi-Tenant Update | P0 | 8 | Day 8 | MEDIUM |
|
||||
| **10** | Kanban Workflow + Sprint Management | P1 | 8 | Day 9 | LOW |
|
||||
|
||||
**Total Days**: 5 days (Days 6-10)
|
||||
**Total Hours**: 38-40 hours
|
||||
**Critical Path**: Day 6 → Day 8 → Day 9 → Day 10
|
||||
|
||||
---
|
||||
|
||||
## Milestone Completion Status
|
||||
|
||||
### M1.1 - Core Project Module (Days 1-10)
|
||||
|
||||
**Progress**: 83% → 100% (after Day 10)
|
||||
|
||||
**Completed** (Days 1-5):
|
||||
- ✅ Domain layer (Projects, Epics, Stories, Tasks)
|
||||
- ✅ Infrastructure layer (EF Core, PostgreSQL)
|
||||
- ✅ Application layer (CQRS commands/queries)
|
||||
- ✅ API layer (RESTful endpoints)
|
||||
- ✅ Unit tests (96.98% coverage)
|
||||
- ✅ JWT authentication
|
||||
- ✅ Refresh token mechanism
|
||||
- ✅ RBAC system (5 tenant roles)
|
||||
|
||||
**Remaining** (Days 6-10):
|
||||
- [ ] Role Management API (Day 6)
|
||||
- [ ] Email verification (Day 7)
|
||||
- [ ] Project-level roles (Day 8)
|
||||
- [ ] Multi-tenant Projects update (Day 9)
|
||||
- [ ] Sprint management (Day 10)
|
||||
|
||||
**After Day 10**:
|
||||
- ✅ M1.1 **100% COMPLETE**
|
||||
- ✅ Ready for M1.2 (SSO Integration)
|
||||
- ✅ Ready for M2 (MCP Server)
|
||||
|
||||
---
|
||||
|
||||
## Days 11-12: M2 MCP Server Foundation (Optional Extension)
|
||||
|
||||
**Duration**: 16 hours (2 days)
|
||||
**Priority**: P0 (Critical for M2 milestone)
|
||||
**Dependencies**: Days 6-10 complete
|
||||
|
||||
### Objectives
|
||||
|
||||
1. Design MCP authentication architecture
|
||||
2. Implement MCP token generation
|
||||
3. Create preview and approval workflow
|
||||
4. Implement basic MCP resources
|
||||
5. Implement basic MCP tools
|
||||
|
||||
### High-Level Deliverables
|
||||
|
||||
**MCP Authentication**:
|
||||
- MCP token format: `mcp_<tenant_slug>_<random_32_chars>`
|
||||
- Token scopes: read, create, update, delete, execute
|
||||
- Token expiration: 90 days (configurable)
|
||||
- Token revocation
|
||||
|
||||
**Database**:
|
||||
```sql
|
||||
CREATE TABLE identity.mcp_tokens (
|
||||
id UUID PRIMARY KEY,
|
||||
tenant_id UUID NOT NULL,
|
||||
token_hash VARCHAR(500) NOT NULL UNIQUE,
|
||||
name VARCHAR(100) NOT NULL,
|
||||
scopes JSONB NOT NULL,
|
||||
expires_at TIMESTAMP NOT NULL,
|
||||
created_by_user_id UUID NOT NULL,
|
||||
created_at TIMESTAMP NOT NULL,
|
||||
last_used_at TIMESTAMP NULL
|
||||
);
|
||||
```
|
||||
|
||||
**Preview System**:
|
||||
```sql
|
||||
CREATE TABLE mcp.previews (
|
||||
id UUID PRIMARY KEY,
|
||||
tenant_id UUID NOT NULL,
|
||||
mcp_token_id UUID NOT NULL,
|
||||
operation VARCHAR(100) NOT NULL,
|
||||
entity_type VARCHAR(50) NOT NULL,
|
||||
entity_id UUID NULL,
|
||||
diff JSONB NOT NULL,
|
||||
status VARCHAR(20) NOT NULL, -- Pending, Approved, Rejected
|
||||
created_at TIMESTAMP NOT NULL,
|
||||
reviewed_by_user_id UUID NULL,
|
||||
reviewed_at TIMESTAMP NULL
|
||||
);
|
||||
```
|
||||
|
||||
**MCP Resources** (Read-only):
|
||||
- `projects.search` - Search projects
|
||||
- `projects.get` - Get project details
|
||||
- `tasks.list` - List tasks
|
||||
- `tasks.get` - Get task details
|
||||
- `reports.daily` - Daily progress report
|
||||
|
||||
**MCP Tools** (Write with preview):
|
||||
- `create_task` - Create task (requires approval)
|
||||
- `update_task_status` - Update task status (requires approval)
|
||||
- `add_comment` - Add comment to task (auto-approved)
|
||||
- `assign_task` - Assign task to user (requires approval)
|
||||
|
||||
**API Endpoints**:
|
||||
1. `POST /api/mcp/tokens` - Generate MCP token
|
||||
2. `GET /api/mcp/tokens` - List tokens
|
||||
3. `DELETE /api/mcp/tokens/{tokenId}` - Revoke token
|
||||
4. `POST /api/mcp/preview` - Create preview for approval
|
||||
5. `POST /api/mcp/preview/{previewId}/approve` - Approve preview
|
||||
6. `POST /api/mcp/preview/{previewId}/reject` - Reject preview
|
||||
7. `GET /api/mcp/resources/{resourceId}` - MCP resource endpoint
|
||||
8. `POST /api/mcp/tools/{toolName}` - MCP tool endpoint
|
||||
|
||||
**Tests**:
|
||||
- 40+ integration tests
|
||||
- MCP authentication tests
|
||||
- Preview workflow tests
|
||||
- Resource access tests
|
||||
- Tool execution tests
|
||||
|
||||
### Success Criteria
|
||||
|
||||
- ✅ MCP tokens generated and validated
|
||||
- ✅ Preview workflow works (create → approve/reject → execute)
|
||||
- ✅ All MCP resources accessible
|
||||
- ✅ All MCP tools functional
|
||||
- ✅ 100% test coverage
|
||||
- ✅ **M2.1 Foundation COMPLETE**
|
||||
|
||||
---
|
||||
|
||||
## Risk Management
|
||||
|
||||
### High-Risk Items
|
||||
|
||||
| Risk | Impact | Probability | Mitigation |
|
||||
|------|--------|-------------|------------|
|
||||
| Day 8 complexity (project roles) | HIGH | MEDIUM | Start simple, iterate later |
|
||||
| Email service delays (Day 7) | MEDIUM | MEDIUM | Use SMTP fallback |
|
||||
| Scope creep (Days 11-12) | HIGH | HIGH | Strictly time-box, defer to Sprint 3 |
|
||||
| Cross-tenant bugs (Day 9) | HIGH | LOW | Comprehensive integration tests |
|
||||
|
||||
### Mitigation Strategies
|
||||
|
||||
1. **Daily check-ins**: Review progress at end of each day
|
||||
2. **Time-boxing**: Strictly limit each day to 8 hours
|
||||
3. **Test-first approach**: Write tests before implementation
|
||||
4. **Code reviews**: Backend agent reviews all code
|
||||
5. **Incremental delivery**: Deploy after each day
|
||||
|
||||
---
|
||||
|
||||
## Success Metrics
|
||||
|
||||
### Sprint Success Criteria (Days 6-10)
|
||||
|
||||
- ✅ All deliverables completed on time
|
||||
- ✅ Zero critical bugs in production
|
||||
- ✅ 100% test coverage maintained
|
||||
- ✅ M1.1 milestone 100% complete
|
||||
- ✅ Ready for M2 MCP integration
|
||||
|
||||
### Quality Metrics
|
||||
|
||||
- **Test Coverage**: ≥ 85% (current: 96.98%)
|
||||
- **API Response Time**: < 200ms (p95)
|
||||
- **Bug Density**: ≤ 0.5 bugs per feature
|
||||
- **Code Quality**: No SonarQube violations
|
||||
- **Documentation**: 100% API endpoints documented
|
||||
|
||||
### Business Metrics
|
||||
|
||||
- **Feature Completion Rate**: 100% (no deferred features)
|
||||
- **Development Velocity**: 5 features in 5 days
|
||||
- **Time to Market**: M1.1 completed in 10 days (on schedule)
|
||||
- **Customer Value**: Complete authentication + authorization + role management
|
||||
|
||||
---
|
||||
|
||||
## Recommendations
|
||||
|
||||
### Immediate Actions (Day 6)
|
||||
|
||||
1. ✅ Approve Day 6 planning document
|
||||
2. ✅ Assign Role Management API to backend agent
|
||||
3. ✅ Begin implementation (6-8 hours)
|
||||
4. ✅ Deploy to development environment
|
||||
|
||||
### Medium-Term Actions (Days 7-10)
|
||||
|
||||
1. Review and approve each day's plan before starting
|
||||
2. Daily progress check-ins
|
||||
3. Continuous integration testing
|
||||
4. Code reviews after each feature
|
||||
|
||||
### Long-Term Actions (M2)
|
||||
|
||||
1. Plan M2 MCP integration (16-hour sprint)
|
||||
2. Design AI agent interaction patterns
|
||||
3. Implement preview and approval workflow
|
||||
4. Test ChatGPT/Claude integration
|
||||
|
||||
---
|
||||
|
||||
## Alternative Scenarios
|
||||
|
||||
### Scenario 1: Days 11-12 Deferred
|
||||
|
||||
**If** scope exceeds 10 days:
|
||||
- **Action**: Defer MCP foundation to Sprint 3
|
||||
- **Impact**: Delays M2 milestone by 1-2 weeks
|
||||
- **Mitigation**: Focus on M1.1 completion first
|
||||
|
||||
### Scenario 2: Email Service Issues (Day 7)
|
||||
|
||||
**If** SendGrid integration fails:
|
||||
- **Action**: Use SMTP fallback (Gmail or local SMTP)
|
||||
- **Impact**: Slower email delivery, no analytics
|
||||
- **Mitigation**: Implement SendGrid in Sprint 3
|
||||
|
||||
### Scenario 3: Project Roles Too Complex (Day 8)
|
||||
|
||||
**If** role inheritance exceeds 8 hours:
|
||||
- **Action**: Simplify to basic project roles (no inheritance)
|
||||
- **Impact**: TenantOwner must be explicitly added to projects
|
||||
- **Mitigation**: Add inheritance in Sprint 3
|
||||
|
||||
---
|
||||
|
||||
## Conclusion
|
||||
|
||||
**Days 7-10 Roadmap**: Comprehensive plan to complete M1.1 milestone
|
||||
|
||||
**Key Milestones**:
|
||||
- Day 7: Email infrastructure
|
||||
- Day 8: Project-level authorization
|
||||
- Day 9: Multi-tenant Projects
|
||||
- Day 10: Sprint management
|
||||
- **M1.1 100% COMPLETE**
|
||||
|
||||
**Next Sprint** (M1.2 - Optional):
|
||||
- Days 11-12: MCP Server foundation
|
||||
- M2 milestone kickoff
|
||||
|
||||
**Strategic Value**:
|
||||
- Complete authentication/authorization stack
|
||||
- Enable multi-tenant SaaS operations
|
||||
- Prepare for AI/MCP integration
|
||||
- Deliver enterprise-grade features
|
||||
|
||||
---
|
||||
|
||||
**Document Status**: ✅ Planning Complete - Ready for Execution
|
||||
|
||||
**Prepared By**: Product Manager Agent
|
||||
**Date**: 2025-11-03
|
||||
**Version**: 1.0
|
||||