sprint_id: sprint_2
|
|
milestone: M1
|
|
status: not_started
|
|
created_date: 2025-11-05
|
|
target_end_date: 2025-11-27
|
|
completion_date: null
|
|
---
|
|
|
|
# Sprint 2: M1 Audit Log & Sprint Management
|
|
|
|
**Milestone**: M1 - Core Project Module
|
|
**Goal**: Complete M1 remaining features - Audit Log MVP (Phase 1-2) and Sprint Management Module to achieve 100% M1 milestone completion.
|
|
|
|
## Sprint Objectives
|
|
|
|
1. **Audit Log MVP** - Implement foundation audit capabilities (Phase 1-2) for compliance and debugging
|
|
2. **Sprint Management Module** - Enable agile sprint planning, tracking, and burndown analytics
|
|
3. **M1 Completion** - Achieve 100% M1 milestone and production readiness
|
|
|
|
## Stories
|
|
- [ ] [story_1](sprint_2_story_1.md) - Audit Log Foundation (Phase 1) - `not_started`
|
|
- [ ] [story_2](sprint_2_story_2.md) - Audit Log Core Features (Phase 2) - `not_started`
|
|
- [ ] [story_3](sprint_2_story_3.md) - Sprint Management Module - `not_started`
|
|
|
|
**Progress**: 0/3 completed (0%)
|
|
|
|
## Sprint Scope Summary
|
|
|
|
### Story 1: Audit Log Foundation (Phase 1)
|
|
**Estimated**: 3-4 days (Day 23-26)
|
|
**Owner**: Backend Team
|
|
|
|
Build the foundation for audit logging:
|
|
- Database schema (AuditLogs table with PostgreSQL JSONB)
|
|
- EF Core SaveChangesInterceptor for automatic logging
|
|
- Basic INSERT/UPDATE/DELETE tracking
|
|
- Unit tests and performance benchmarks
|
|
|
|
### Story 2: Audit Log Core Features (Phase 2)
|
|
**Estimated**: 3-4 days (Day 27-30)
|
|
**Owner**: Backend Team
|
|
|
|
Add core audit features:
|
|
- Changed fields detection (old vs new values JSON diff)
|
|
- User context tracking (who made the change)
|
|
- Multi-tenant isolation for audit logs
|
|
- Query API for retrieving audit history
|
|
- Integration tests
|
|
|
|
### Story 3: Sprint Management Module
|
|
**Estimated**: 3-4 days (Day 31-34)
|
|
**Owner**: Backend Team
|
|
|
|
Build Sprint management capabilities:
|
|
- Sprint entity and domain logic
|
|
- 9 CQRS API endpoints (Create, Update, Delete, Get, List, etc.)
|
|
- Burndown chart data calculation
|
|
- SignalR integration for real-time Sprint updates
|
|
- Integration tests
|
|
|
|
## Timeline
|
|
|
|
- **Week 1 (Nov 9-15)**: Story 1 - Audit Log Foundation
|
|
- **Week 2 (Nov 16-22)**: Story 2 - Audit Log Core Features
|
|
- **Week 3 (Nov 23-27)**: Story 3 - Sprint Management Module
|
|
|
|
## Definition of Done
|
|
|
|
- [ ] All 3 stories completed with acceptance criteria met
|
|
- [ ] All tests passing (>= 90% coverage)
|
|
- [ ] No CRITICAL or HIGH severity bugs
|
|
- [ ] Code reviewed and approved
|
|
- [ ] Multi-tenant security verified
|
|
- [ ] API documentation updated
|
|
- [ ] M1 milestone 100% complete
|
|
|
|
## Dependencies
|
|
|
|
**Prerequisites**:
|
|
- ✅ ProjectManagement Module 95% Production Ready (Day 16)
|
|
- ✅ SignalR Backend 100% Complete (Day 17)
|
|
- ✅ Multi-Tenant Security Complete (Day 15)
|
|
- ✅ Identity & RBAC Production Ready (Day 9)
|
|
|
|
**Technical Requirements**:
|
|
- PostgreSQL JSONB support
|
|
- EF Core 9.0 Interceptors API
|
|
- Redis for distributed locking
|
|
- SignalR Hub infrastructure
|
|
|
|
## Notes
|
|
|
|
### M1 Completion Status
|
|
Upon Sprint 2 completion, M1 should achieve 100%:
|
|
- ✅ Epic/Story/Task three-tier hierarchy (Day 15-20)
|
|
- ✅ Kanban board with real-time updates (Day 13, 18-20)
|
|
- ⏳ Audit log MVP (Sprint 2, Story 1-2)
|
|
- ⏳ Sprint management CRUD (Sprint 2, Story 3)
|
|
|
|
**M1 Target Completion**: 2025-11-27
|
|
|
|
### Story Creation
|
|
Backend agent will create detailed Story and Task files for this Sprint based on:
|
|
- Audit Log technical design (Day 14 research)
|
|
- Sprint Management requirements (product.md Day 31-34 plan)
|
|
|
|
---
|
|
|
|
**Created**: 2025-11-05 by Product Manager Agent
|
|
**Next Review**: 2025-11-15 (mid-sprint checkpoint)
|