ColaFlow Enterprise Multi-Tenant - 10-Day Implementation Plan
Plan Date: 2025-11-03 Plan Horizon: 10 working days (2025-11-03 to 2025-11-13) Plan Status: Active - Day 1 Complete Project: ColaFlow M1.2 - Enterprise Multi-Tenant Architecture Owner: Product Manager + Technical Leads
Executive Summary
This document provides a detailed 10-day implementation plan for ColaFlow's enterprise multi-tenant architecture upgrade, including multi-tenancy, SSO integration, and MCP authentication. The plan covers backend development (Days 1-4), frontend development (Days 5-7), integration testing (Day 8), database migration (Day 9), and production validation (Day 10).
Overall Progress: 10% complete (Day 1 of 10) Status: On Track Projected Completion: 2025-11-13
Table of Contents
- Plan Overview
- Day-by-Day Breakdown
- Dependencies and Critical Path
- Resource Allocation
- Risk Management
- Success Criteria
- Communication Plan
Plan Overview
Phases
| Phase | Days | Owner | Deliverables | Status |
|---|---|---|---|---|
| Phase 1: Backend Foundation | 1-4 | Backend Team | Domain, Application, Infrastructure, Migration | Day 1 Complete |
| Phase 2: Frontend Development | 5-7 | Frontend Team | Auth UI, Settings, MCP Token Management | Planned |
| Phase 3: Integration & Testing | 8 | QA + All Teams | E2E tests, Security tests, Bug fixes | Planned |
| Phase 4: Production Deployment | 9-10 | DevOps + All Teams | Migration, Monitoring, Validation | Planned |
Milestones
| Milestone | Target Date | Dependencies | Deliverables |
|---|---|---|---|
| M1.2.1: Backend Complete | Day 4 (2025-11-06) | Domain, Application, Infrastructure | Functional APIs, Tests passing |
| M1.2.2: Frontend Complete | Day 7 (2025-11-09) | Backend APIs ready | Full UI implementation |
| M1.2.3: Integration Complete | Day 8 (2025-11-10) | Backend + Frontend | All tests passing |
| M1.2.4: Production Ready | Day 10 (2025-11-13) | Testing complete | Live in production |
Key Metrics
| Metric | Target | Current | Status |
|---|---|---|---|
| Backend Completion | 100% by Day 4 | 25% (Day 1) | On Track |
| Frontend Completion | 100% by Day 7 | 0% | Scheduled |
| Test Coverage | >80% | 100% (Domain) | Exceeds Target |
| Integration Test Pass Rate | 100% | N/A | Scheduled Day 8 |
| Production Deployment | Day 10 | N/A | Scheduled |
Day-by-Day Breakdown
Day 1: Domain Layer (COMPLETE)
Date: 2025-11-03 Status: COMPLETE Owner: Backend Engineer Estimated Time: 6 hours Actual Time: 6 hours
Deliverables
-
Projects Created:
ColaFlow.Modules.Identity.DomainColaFlow.Modules.Identity.Application(empty scaffold)ColaFlow.Modules.Identity.Infrastructure(empty scaffold)ColaFlow.Modules.Identity.Domain.Tests
-
Domain Layer (27 files):
- Tenant aggregate root + 4 value objects + 3 enums + 7 domain events
- User aggregate root + 3 value objects + 2 enums + 4 domain events
- 2 repository interfaces (ITenantRepository, IUserRepository)
-
Unit Tests (44 tests):
- TenantTests (15 tests)
- TenantSlugTests (7 tests)
- UserTests (22 tests)
- Result: 44/44 passing (100%)
Acceptance Criteria
- Domain entities follow DDD principles (aggregate roots, value objects)
- All business rules enforced at domain level
- Unit tests cover all critical paths
- No compilation warnings or errors
- Code follows Clean Architecture principles
Status: All criteria met
Day 2: Infrastructure Layer + TenantContext
Date: 2025-11-04 Status: PLANNED Owner: Backend Engineer Estimated Time: 4-5 hours
Deliverables
-
TenantContext Service
- Resolve current tenant from JWT claims
- Inject into DbContext
- Handle missing tenant (throw exception)
- Unit tests (5 tests)
-
EF Core Global Query Filter
- Configure in
ApplicationDbContext.OnModelCreating - Apply to all
IHasTenantentities:.Where(e => e.TenantId == _tenantContext.CurrentTenantId) - Test with sample data
- Configure in
-
Repository Implementations
TenantRepository(9 methods)UserRepository(10 methods)- Integration tests (20 tests)
-
Database Configuration
- Connection string management
- DbContext configuration
- EF Core migrations setup
Tasks Checklist
- Create
TenantContext.csin Infrastructure - Inject TenantContext into ApplicationDbContext
- Configure Global Query Filter for all entities
- Implement TenantRepository with all 9 methods
- Implement UserRepository with all 10 methods
- Write integration tests for repositories
- Test Global Query Filter with sample data
- Verify cross-tenant isolation (Tenant A cannot see Tenant B's data)
- Update connection strings in appsettings.json
- Run all tests (Unit + Integration)
Acceptance Criteria
- TenantContext resolves tenant from HttpContext
- Global Query Filter applied to all queries automatically
- Repositories pass all integration tests
- Cross-tenant queries return empty results (isolation verified)
- No database queries missing
WHERE tenant_id = ? - Performance: Queries complete in <50ms with proper indexes
Expected Files Created
Infrastructure/
Services/
TenantContext.cs (new)
Persistence/
ApplicationDbContext.cs (updated)
Repositories/
TenantRepository.cs (new)
UserRepository.cs (new)
Configuration/
TenantEntityConfiguration.cs (new)
UserEntityConfiguration.cs (new)
Tests/Integration/
Repositories/
TenantRepositoryTests.cs (new, 10 tests)
UserRepositoryTests.cs (new, 10 tests)
TenantContextTests.cs (new, 5 tests)
Dependencies
- Day 1 Domain layer complete
- PostgreSQL database running locally
Risks
- Global Query Filter might be bypassed accidentally (mitigation: code review)
- Performance issues if indexes not configured correctly (mitigation: EXPLAIN ANALYZE)
Day 3: Application Layer + Tenant Registration API
Date: 2025-11-05 Status: PLANNED Owner: Backend Engineer Estimated Time: 4-5 hours
Deliverables
-
Application Layer (Commands)
RegisterTenantCommand+ Handler + Validator (FluentValidation)UpdateSsoConfigCommand+ Handler + ValidatorCreateUserCommand+ Handler + ValidatorCreateUserFromSsoCommand+ Handler
-
Application Layer (Queries)
GetTenantBySlugQuery+ HandlerGetTenantByIdQuery+ HandlerCheckSlugAvailabilityQuery+ HandlerGetUserByEmailQuery+ Handler
-
API Endpoints (TenantController)
POST /api/tenants- Register new tenantGET /api/tenants/{id}- Get tenant detailsPOST /api/tenants/check-slug- Check slug availabilityPUT /api/tenants/{id}/sso-config- Configure SSO
-
Validation
- FluentValidation for all commands
- Custom validators (slug format, email format)
- Error responses with validation details
Tasks Checklist
- Create Commands folder in Application layer
- Implement RegisterTenantCommand + Handler
- Implement UpdateSsoConfigCommand + Handler
- Implement CreateUserCommand + Handler
- Create Queries folder in Application layer
- Implement GetTenantBySlugQuery + Handler
- Implement CheckSlugAvailabilityQuery + Handler
- Create TenantController in API project
- Implement all 4 tenant endpoints
- Add FluentValidation for all commands
- Write unit tests for commands/queries (20 tests)
- Write API integration tests (10 tests)
- Update API documentation (Scalar/Swagger)
- Test with Postman/Insomnia
Acceptance Criteria
- All commands execute successfully
- Validation errors return 400 Bad Request with details
- Slug availability check returns true/false correctly
- Tenant registration creates both tenant and admin user
- API returns proper HTTP status codes (200, 201, 400, 404)
- All unit tests pass
- All API integration tests pass
- API documentation updated
Expected Files Created
Application/
Tenants/
Commands/
RegisterTenant/
RegisterTenantCommand.cs (new)
RegisterTenantCommandHandler.cs (new)
RegisterTenantCommandValidator.cs (new)
UpdateSsoConfig/
UpdateSsoConfigCommand.cs (new)
UpdateSsoConfigCommandHandler.cs (new)
Queries/
GetTenantBySlug/
GetTenantBySlugQuery.cs (new)
GetTenantBySlugQueryHandler.cs (new)
CheckSlugAvailability/
CheckSlugAvailabilityQuery.cs (new)
CheckSlugAvailabilityQueryHandler.cs (new)
API/
Controllers/
TenantsController.cs (new)
Dependencies
- Day 2 Infrastructure layer complete
- TenantRepository and UserRepository working
Risks
- Slug validation regex might be too restrictive (mitigation: user testing)
- SSO config validation complex (mitigation: provider-specific validators)
Day 4: Database Migration Preparation + Performance Testing
Date: 2025-11-06 Status: PLANNED Owner: Backend Engineer + DBA Estimated Time: 4-5 hours
Deliverables
-
EF Core Migrations
- Generate migration:
AddMultiTenancySupport - Review generated SQL scripts
- Test migration in local database
- Test rollback procedure
- Generate migration:
-
Manual SQL Scripts
- 01_create_tenants.sql
- 02_insert_default_tenant.sql
- 03_add_tenant_columns.sql
- 04_migrate_data.sql
- 05_validate_migration.sql
- 06_set_not_null.sql
- 07_create_indexes.sql
- 08_update_constraints.sql
- 09_add_sso_columns.sql
- 10_create_mcp_tables.sql
- 11_verify_performance.sql
-
Performance Testing
- Load sample data (100 tenants × 10,000 records)
- Run EXPLAIN ANALYZE on common queries
- Verify index usage (no sequential scans)
- Benchmark query performance (<50ms target)
- Stress test: 10,000 requests with tenant filtering
-
Staging Environment Testing
- Clone production-like database to staging
- Run full migration on staging
- Validate data integrity (0 rows with NULL tenant_id)
- Test rollback procedure
- Document any issues
Tasks Checklist
- Generate EF Core migration:
dotnet ef migrations add AddMultiTenancySupport - Review generated migration code
- Create manual SQL scripts (11 scripts)
- Test migration on local database
- Load sample data: 100 tenants, 10,000 records each
- Run EXPLAIN ANALYZE on:
SELECT * FROM projects WHERE tenant_id = 'xxx'SELECT * FROM issues WHERE tenant_id = 'xxx' AND status = 1SELECT * FROM users WHERE tenant_id = 'xxx' AND email = 'test@acme.com'
- Verify all queries use index scans (not sequential scans)
- Benchmark query performance: <50ms p95
- Stress test: 10,000 concurrent requests
- Clone production database to staging
- Run full migration on staging
- Run validation script: check for NULL tenant_id
- Test rollback: restore from backup
- Document migration steps
- Create runbook for production migration
Acceptance Criteria
- EF Core migration generated successfully
- All SQL scripts reviewed and approved
- Local migration completes without errors
- No NULL tenant_id values after migration
- Query performance meets target (<50ms p95)
- All queries use appropriate indexes
- Staging migration successful (no data loss)
- Rollback procedure tested and documented
- Runbook created for production deployment
Expected Files Created
Infrastructure/
Persistence/
Migrations/
YYYYMMDDHHMMSS_AddMultiTenancySupport.cs (new)
migration_scripts/
01_create_tenants.sql (new)
02_insert_default_tenant.sql (new)
03_add_tenant_columns.sql (new)
04_migrate_data.sql (new)
05_validate_migration.sql (new)
06_set_not_null.sql (new)
07_create_indexes.sql (new)
08_update_constraints.sql (new)
09_add_sso_columns.sql (new)
10_create_mcp_tables.sql (new)
99_rollback.sql (new)
docs/
deployment/
migration-runbook.md (new)
rollback-procedure.md (new)
performance-benchmarks.md (new)
Dependencies
- Day 3 Application layer complete
- Staging environment available
- DBA review scheduled
Risks
- Migration scripts might fail on large databases (mitigation: test with production-sized data)
- Performance issues discovered late (mitigation: early performance testing on Day 4)
- Rollback procedure untested (mitigation: test rollback on staging)
Day 5: Frontend Core Infrastructure + Authentication Pages
Date: 2025-11-07 Status: PLANNED Owner: Frontend Engineer Estimated Time: 8 hours
Deliverables
-
Core Infrastructure (Morning - 3-4 hours)
- API client with Axios interceptors
- Auth Store (Zustand)
- TypeScript types (auth.ts, api.ts, mcp.ts)
- Next.js middleware for route protection
-
Authentication Pages (Afternoon - 4-5 hours)
- Login page (local + SSO buttons)
- Signup page (3-step wizard)
- SSO callback page
- Suspended tenant page
Tasks Checklist - Morning
API Client (lib/api-client.ts):
- Create Axios instance with base URL
- Add request interceptor (inject Authorization header)
- Add response interceptor (handle 401, refresh token)
- Implement token refresh logic (queue concurrent requests)
- Add error handling (network errors, timeouts)
- Unit tests (5 tests)
Auth Store (stores/useAuthStore.ts):
- Define AuthState interface (user, tenant, accessToken)
- Implement login action
- Implement logout action
- Implement updateToken action (for refresh)
- NO persistence for accessToken (security)
- Unit tests (8 tests)
TypeScript Types:
- Create
types/auth.ts(User, Tenant, LoginRequest, LoginResponse) - Create
types/api.ts(ApiResponse, ApiError) - Create
types/mcp.ts(McpToken, McpPermission, AuditLog) - Export all types in
types/index.ts
Next.js Middleware (app/middleware.ts):
- Protect routes requiring authentication
- Validate JWT token (jose library)
- Check tenant status (active/suspended)
- Redirect logic:
- Unauthenticated + protected route →
/login?redirect=/original - Authenticated +
/login→/dashboard - Suspended tenant →
/suspended
- Unauthenticated + protected route →
- Unit tests (6 tests)
Tasks Checklist - Afternoon
Login Page (app/(auth)/login/page.tsx):
- Create login form (email, password)
- Add SSO buttons (Azure AD, Google, Okta)
- "Remember me" checkbox
- "Forgot password" link
- Form validation with Zod
- Loading states
- Error handling (toast notifications)
- Responsive design (mobile-friendly)
- Integration with Auth Store
- Unit tests (10 tests)
Signup Page (app/(auth)/signup/page.tsx):
- Step 1: Company info (name, slug)
- Step 2: Admin account (name, email, password)
- Step 3: Plan selection
- Progress indicator (steps)
- Real-time slug validation (debounced 500ms)
- Password strength indicator
- Form validation with Zod
- Submit registration
- Success animation + redirect
- Unit tests (12 tests)
SSO Callback Page (app/(auth)/auth/callback/page.tsx):
- Parse URL parameters (?token=xxx&state=yyy)
- Validate state parameter (CSRF protection)
- Store token in Auth Store
- Redirect to original page or dashboard
- Error handling (SSO failed)
- Loading state
- Unit tests (5 tests)
Acceptance Criteria
Morning (Infrastructure):
- API client automatically injects Authorization header
- 401 errors trigger automatic token refresh
- Token refresh only happens once for concurrent requests
- Failed refresh redirects to
/login - Auth Store persists user info (but not token)
- Middleware protects all dashboard routes
- JWT validation works correctly
Afternoon (Pages):
- Login works with local credentials
- SSO buttons redirect to backend SSO endpoints
- Signup wizard navigates through 3 steps
- Slug validation shows "Available" or "Taken" in real-time
- Password strength indicator works (weak/medium/strong)
- SSO callback handles success and error cases
- All forms have proper validation and error messages
- Mobile responsive (tested on 375px width)
Expected Files Created
lib/
api-client.ts (new)
query-client.ts (new)
utils.ts (new)
validations.ts (new)
stores/
useAuthStore.ts (new)
useUiStore.ts (new)
types/
auth.ts (new)
api.ts (new)
mcp.ts (new)
index.ts (new)
app/
middleware.ts (new)
(auth)/
login/page.tsx (new)
signup/page.tsx (new)
auth/callback/page.tsx (new)
suspended/page.tsx (new)
components/
auth/
SsoButton.tsx (new)
TenantSlugInput.tsx (new)
PasswordStrengthIndicator.tsx (new)
hooks/
auth/
useLogin.ts (new)
useSignup.ts (new)
useLoginWithSso.ts (new)
services/
auth.service.ts (new)
__tests__/
lib/api-client.test.ts (new)
stores/useAuthStore.test.ts (new)
components/auth/SsoButton.test.tsx (new)
pages/login.test.tsx (new)
pages/signup.test.tsx (new)
Dependencies
- Backend APIs ready:
/api/auth/login,/api/tenants/check-slug,/api/tenants(POST) - Design specs complete (from docs/design/)
- shadcn/ui components installed
Risks
- Token refresh logic complex (mitigation: test extensively)
- SSO redirect flow confusing (mitigation: clear loading states)
- Slug validation debouncing issues (mitigation: use TanStack Query with proper config)
Day 6: Frontend Settings + SSO Configuration
Date: 2025-11-08 Status: PLANNED Owner: Frontend Engineer Estimated Time: 6-7 hours
Deliverables
-
Organization Settings Page
- Tabs: General, SSO, Billing, Usage
- SSO tab with configuration form
- Dynamic form fields based on provider
- Test connection button
- Save configuration
-
Components
- SsoConfigForm (dynamic fields)
- ProviderSpecificFields (OIDC vs SAML)
- TestConnectionButton
- AllowedDomainsInput
Tasks Checklist
Settings Layout (app/(dashboard)/settings/layout.tsx):
- Create settings sidebar navigation
- Tabs: General, SSO, Billing, Usage
- Active tab highlighting
- Responsive layout
SSO Configuration Page (app/(dashboard)/settings/organization/page.tsx):
- Provider selection dropdown (Azure AD, Google, Okta, SAML)
- Dynamic form fields based on provider:
- OIDC: Authority URL, Client ID, Client Secret, Metadata URL
- SAML: Entity ID, SSO URL, X.509 Certificate, Metadata URL
- Auto-provision users toggle
- Allowed email domains input (TagInput)
- Callback URL display (read-only, copy button)
- Test connection button (with loading state)
- Save configuration button
- Success/error toast notifications
- Form validation with Zod
- Unit tests (15 tests)
Components:
SsoConfigForm (components/settings/SsoConfigForm.tsx):
- Provider selection logic
- Conditional field rendering (OIDC vs SAML)
- Form state management (React Hook Form)
- Validation
- Submit handler
- Unit tests (10 tests)
AllowedDomainsInput (components/settings/AllowedDomainsInput.tsx):
- Tag input for domains
- Add/remove domain
- Domain validation (@domain.com format)
- Unit tests (5 tests)
TestConnectionButton (components/settings/TestConnectionButton.tsx):
- Call
/api/tenants/{id}/sso-config/testendpoint - Loading state (spinner)
- Success modal with details (metadata reachable, certificate valid, etc.)
- Error modal with troubleshooting steps
- Unit tests (5 tests)
Acceptance Criteria
- Provider selection changes form fields dynamically
- All form fields validate correctly
- Test connection shows success/error with details
- Save configuration updates tenant SSO config
- Callback URL is displayed and copyable
- Allowed domains can be added/removed
- Auto-provision toggle works
- Form handles errors gracefully (backend errors, network errors)
- Only Admin users can access (permission check)
- All unit tests pass
Expected Files Created
app/
(dashboard)/
settings/
layout.tsx (new)
organization/page.tsx (new)
sso/page.tsx (new)
components/
settings/
SsoConfigForm.tsx (new)
AllowedDomainsInput.tsx (new)
TestConnectionButton.tsx (new)
SsoProviderLogo.tsx (new)
hooks/
tenants/
useSsoConfig.ts (new)
useTestSsoConnection.ts (new)
useUpdateSsoConfig.ts (new)
services/
tenant.service.ts (new)
__tests__/
components/settings/SsoConfigForm.test.tsx (new)
pages/settings/organization.test.tsx (new)
Dependencies
- Backend APIs ready: GET/PUT
/api/tenants/{id}/sso-config, POST/api/tenants/{id}/sso-config/test - shadcn/ui components: Select, Tabs, Form, Alert
- Day 5 Auth infrastructure complete
Risks
- SSO form complexity (many fields, validation) (mitigation: provider-specific Zod schemas)
- Test connection endpoint slow (mitigation: show loading state, timeout after 10s)
Day 7: Frontend MCP Token Management
Date: 2025-11-09 Status: PLANNED Owner: Frontend Engineer Estimated Time: 7-8 hours
Deliverables
-
MCP Tokens List Page
- Token list table
- Generate token button
- Revoke token action
- Filter by status (Active/Revoked/Expired)
-
Create Token Dialog
- 3-step wizard (Token info, Permissions, Review)
- Permission matrix (resource × operations)
- Token display (one-time only)
-
Token Details Page
- Token metadata
- Usage statistics
- Audit log table
- Revoke button
Tasks Checklist
MCP Tokens List Page (app/(dashboard)/settings/mcp-tokens/page.tsx):
- Token list table (@tanstack/react-table)
- Columns: Name, Permissions, Last Used, Expires, Status, Actions
- Generate token button (opens dialog)
- Revoke button for each token
- Filter dropdown (All, Active, Revoked, Expired)
- Empty state (no tokens)
- Loading skeleton
- Unit tests (8 tests)
Create Token Dialog (components/mcp/CreateTokenDialog.tsx):
- 3-step wizard UI
- Step 1: Token info (name, description, expiration)
- Step 2: Permissions (permission matrix)
- Step 3: Review & create
- Token display modal (one-time, with warning)
- Copy to clipboard button
- Download as .env file button
- "I've saved the token" checkbox
- Form validation
- Unit tests (12 tests)
Permission Matrix (components/mcp/McpPermissionMatrix.tsx):
- Checkbox grid (resources × operations)
- Resources: Projects, Issues, Documents, Reports, Sprints, Comments
- Operations: Read, Create, Update, Delete, Search
- "Select all" shortcuts (per resource, per operation)
- Permission templates (Read Only, Read+Write, Custom)
- Unit tests (5 tests)
Token Display (components/mcp/TokenDisplay.tsx):
- Display generated token (once only)
- Copy button (with success toast)
- Download button (generates .env file)
- Warning message ("You won't see this again")
- Checkbox: "I've saved this token"
- Close button (enabled only after checkbox)
- Unit tests (5 tests)
Token Details Page (app/(dashboard)/settings/mcp-tokens/[id]/page.tsx):
- Token metadata (name, created, expires, status)
- Usage statistics (total calls, last used)
- Activity chart (last 7 days)
- Audit log table (timestamp, action, resource, result)
- Pagination for audit logs
- Revoke button (with confirmation dialog)
- Unit tests (8 tests)
Audit Log Table (components/mcp/AuditLogTable.tsx):
- Table with columns: Timestamp, HTTP Method, Endpoint, Status Code, Duration, IP Address
- Pagination (server-side)
- Date range filter
- Status code filter (200, 401, 403, 500)
- Export to CSV button
- Unit tests (5 tests)
Acceptance Criteria
- Token list loads and displays all tokens
- Generate token wizard works (3 steps)
- Permission matrix selects/deselects correctly
- Generated token displayed only once
- Copy and download buttons work
- Token details page shows metadata and audit logs
- Revoke confirmation dialog works
- Revoked tokens marked as "Revoked" (red badge)
- All unit tests pass
- Mobile responsive
Expected Files Created
app/
(dashboard)/
settings/
mcp-tokens/
page.tsx (new)
[id]/page.tsx (new)
components/
mcp/
CreateTokenDialog.tsx (new)
McpPermissionMatrix.tsx (new)
TokenDisplay.tsx (new)
AuditLogTable.tsx (new)
RevokeTokenDialog.tsx (new)
hooks/
mcp/
useMcpTokens.ts (new)
useCreateMcpToken.ts (new)
useRevokeMcpToken.ts (new)
useMcpAuditLogs.ts (new)
services/
mcp.service.ts (new)
__tests__/
components/mcp/CreateTokenDialog.test.tsx (new)
components/mcp/McpPermissionMatrix.test.tsx (new)
pages/mcp-tokens.test.tsx (new)
Dependencies
- Backend APIs ready: GET/POST
/api/mcp-tokens, DELETE/api/mcp-tokens/{id}, GET/api/mcp-tokens/{id}/audit-logs - shadcn/ui components: Dialog, Table, Checkbox
- Day 6 Settings infrastructure complete
Risks
- Permission matrix UI complex (many checkboxes) (mitigation: clear visual grouping, templates)
- Token display security (prevent screenshots) (mitigation: warning messages only, no technical prevention)
- Audit log pagination performance (mitigation: server-side pagination, limit to 50 per page)
Day 8: Integration Testing + Security Testing
Date: 2025-11-10 Status: PLANNED Owner: QA Engineer + All Teams Estimated Time: 8 hours
Deliverables
-
End-to-End Tests
- Registration → Login → Dashboard flow
- SSO login flow (mocked IdP)
- MCP token creation → Usage → Revocation
- Cross-tenant isolation tests
-
Security Tests
- XSS protection (tokens in memory)
- CSRF protection (SameSite cookies)
- SQL injection (parameterized queries)
- Authorization (tenant isolation)
-
Performance Tests
- API response times (<100ms)
- Frontend render times (<16ms)
- Database query performance (<50ms)
- Load test: 1,000 concurrent users
-
Bug Fixes
- Address all issues found during testing
- Re-test after fixes
Tasks Checklist
E2E Tests (Playwright):
- Test: New tenant registration (3-step wizard)
- Test: Local login → Dashboard
- Test: SSO login (mocked IdP) → Dashboard
- Test: Configure SSO (admin user)
- Test: Generate MCP token (3-step wizard)
- Test: Copy token, download .env file
- Test: Use MCP token to call API (success)
- Test: Revoke token, verify API call fails (401)
- Test: Cross-tenant isolation (Tenant A cannot access Tenant B's data)
- Test: Logout → Clear auth state
Security Tests:
- Test: Access token not in localStorage/sessionStorage/cookies
- Test: Refresh token in httpOnly cookie
- Test: XSS attack simulation (inject script, cannot steal token)
- Test: CSRF attack simulation (forged request, rejected)
- Test: SQL injection attempt (parameterized queries protect)
- Test: Attempt to access other tenant's data (403 Forbidden)
- Test: Attempt to use revoked MCP token (401 Unauthorized)
- Test: JWT signature validation (tampered token rejected)
Performance Tests:
- Test: API response time <100ms (p95)
- Test: Frontend render time <16ms (60fps)
- Test: Database query time <50ms (p95)
- Test: Token validation <10ms
- Load test: 1,000 concurrent users
- Load test: 10,000 API requests with tenant filtering
Integration Tests:
- Test: Frontend calls backend APIs successfully
- Test: Error handling (network errors, 500 errors)
- Test: Token refresh flow (401 → refresh → retry)
- Test: API client retries failed requests
- Test: TanStack Query cache invalidation
Bug Tracking:
- Log all bugs in issue tracker
- Prioritize: P0 (blocker), P1 (critical), P2 (major), P3 (minor)
- Assign to developers
- Re-test after fixes
- Sign-off when all P0/P1 bugs fixed
Acceptance Criteria
- All E2E tests pass (10/10)
- All security tests pass (8/8)
- Performance tests meet targets
- All P0 bugs fixed
- All P1 bugs fixed or scheduled for M1.3
- No regressions in existing features
- Test reports generated and reviewed
Expected Deliverables
tests/
e2e/
registration.spec.ts (new)
login.spec.ts (new)
sso.spec.ts (new)
mcp-tokens.spec.ts (new)
tenant-isolation.spec.ts (new)
security/
xss.spec.ts (new)
csrf.spec.ts (new)
authorization.spec.ts (new)
performance/
api-benchmarks.spec.ts (new)
load-test.spec.ts (new)
reports/
2025-11-10-Testing-Report.md (new)
bug-tracker.csv (new)
Dependencies
- Day 7 Frontend complete
- Day 4 Backend complete
- Test environment ready (staging)
Risks
- Bugs discovered late (mitigation: prioritize fixes, may extend to Day 9 if critical)
- Performance issues (mitigation: profiling, optimization)
- SSO mocking complex (mitigation: use MSW with realistic responses)
Day 9: Database Migration + Production Deployment
Date: 2025-11-11 Status: PLANNED Owner: DBA + Backend Engineer + DevOps Estimated Time: 6-8 hours (includes 30-60 min downtime)
Deliverables
-
Pre-Migration
- Full database backup
- Verify backup integrity
- Copy backup to S3
- Enable maintenance mode
-
Database Migration
- Run 11 SQL migration scripts
- Validate data integrity
- Verify performance (indexes working)
-
Code Deployment
- Deploy backend API (updated code)
- Deploy frontend (updated code)
- Restart services
-
Smoke Tests
- Login test
- Create project test
- API health check
- Frontend loads correctly
Tasks Checklist
Pre-Migration (30 minutes):
- Schedule maintenance window (2 hours, off-peak)
- Notify all users 24 hours in advance
- Enable maintenance mode (503 page)
- Full database backup:
pg_dump -Fc colaflow > backup.dump - Verify backup:
pg_restore --list backup.dump | head -20 - Copy backup to S3:
aws s3 cp backup.dump s3://backups/pre-migration/ - Team on standby (Backend, Frontend, DevOps)
Database Migration (30-60 minutes):
- Run script 01:
psql -f 01_create_tenants.sql - Run script 02:
psql -f 02_insert_default_tenant.sql - Run script 03:
psql -f 03_add_tenant_columns.sql - Run script 04:
psql -f 04_migrate_data.sql - Run script 05:
psql -f 05_validate_migration.sql(check for errors) - Run script 06:
psql -f 06_set_not_null.sql - Run script 07:
psql -f 07_create_indexes.sql - Run script 08:
psql -f 08_update_constraints.sql - Run script 09:
psql -f 09_add_sso_columns.sql - Run script 10:
psql -f 10_create_mcp_tables.sql - Run validation: Check for NULL tenant_id (should be 0 rows)
- Verify indexes: EXPLAIN ANALYZE sample queries
Code Deployment (20 minutes):
- Deploy backend:
dotnet publish -c Release -o /var/www/api - Restart backend:
systemctl restart colaflow-api - Verify backend:
curl https://api.colaflow.com/health - Deploy frontend:
npm run build && rsync -avz out/ /var/www/web/ - Restart frontend:
systemctl restart colaflow-web - Verify frontend:
curl https://colaflow.com
Smoke Tests (20 minutes):
- Test 1: Login with existing user (default tenant)
- Test 2: View projects list (default tenant)
- Test 3: Create new project
- Test 4: View issue board
- Test 5: API health check returns 200
- Test 6: Frontend loads without errors (check browser console)
- Test 7: Database query performance <50ms
Post-Deployment (10 minutes):
- Disable maintenance mode
- Monitor error logs (30 minutes)
- Monitor database performance (pg_stat_statements)
- Monitor API response times (APM dashboard)
- Notify users: Maintenance complete
- Post-deployment retrospective
Acceptance Criteria
- Migration completes successfully (no errors)
- No data loss (validation script passes)
- All smoke tests pass
- API response times normal (<100ms)
- No 500 errors in first hour
- Error rate <1% in first 24 hours
Rollback Plan
If migration fails:
- Stop application (maintenance mode)
- Drop migrated database:
DROP DATABASE colaflow; - Restore from backup:
pg_restore -C -d postgres backup.dump - Deploy previous code version
- Restart services
- Verify rollback successful
- Notify stakeholders
- Schedule post-mortem
Dependencies
- Day 8 testing complete (all P0 bugs fixed)
- Migration scripts reviewed and approved
- Backup strategy verified
- Rollback procedure tested
Risks
- Data loss (mitigation: full backup, tested rollback)
- Extended downtime (mitigation: pre-test migration, have rollback ready)
- Performance issues (mitigation: indexes tested on Day 4)
Day 10: Production Validation + Monitoring
Date: 2025-11-13 Status: PLANNED Owner: All Teams Estimated Time: 4-8 hours (continuous monitoring)
Deliverables
-
Monitoring Setup
- Application error tracking (Sentry)
- Performance monitoring (APM)
- Database monitoring (pg_stat_statements)
- User analytics (PostHog)
-
User Acceptance Testing
- Internal team testing
- Beta user testing (if available)
- Stakeholder demo
-
Documentation
- Update README
- API documentation (Scalar)
- User guides (SSO setup, MCP tokens)
- Admin guides (tenant management)
-
Post-Deployment Review
- Retrospective meeting
- Lessons learned
- Plan for M1.3
Tasks Checklist
Monitoring (Morning):
- Configure error tracking (Sentry):
- Backend errors (500, exceptions)
- Frontend errors (React errors, network failures)
- Error rate alerts (>5% triggers)
- Configure performance monitoring:
- API response times (p50, p95, p99)
- Database query times
- Slow query alerts (>100ms)
- Configure database monitoring:
- pg_stat_statements enabled
- Slow query log analysis
- Index usage monitoring
- Configure user analytics:
- Page views
- User flows (registration, login, SSO)
- Feature usage (MCP tokens created)
Validation Testing (Afternoon):
- Internal team testing:
- All team members register new tenants
- Test SSO configuration (Azure AD, Google)
- Generate MCP tokens
- Report any issues
- Beta user testing (if available):
- Invite 5-10 beta users
- Monitor their usage
- Collect feedback
- Stakeholder demo:
- Present new features to leadership
- Demo multi-tenancy, SSO, MCP tokens
- Discuss roadmap
Documentation:
- Update README.md:
- Multi-tenant architecture overview
- Environment variables
- Deployment instructions
- Update API documentation (Scalar):
- All new endpoints documented
- Request/response examples
- Authentication instructions
- Create user guides:
- "How to configure SSO" (with screenshots)
- "How to generate MCP tokens"
- "How to integrate with Claude/ChatGPT"
- Create admin guides:
- "How to manage tenants"
- "How to troubleshoot SSO issues"
- "How to monitor token usage"
Post-Deployment Review:
- Schedule retrospective meeting (all teams)
- Discuss: What went well?
- Discuss: What could be improved?
- Discuss: What should we do differently next time?
- Document lessons learned
- Plan M1.3 features and timeline
Acceptance Criteria
- Error rate <1% in first 24 hours
- API response times normal (<100ms p95)
- No critical bugs reported
- Internal team successfully uses all features
- Stakeholder demo successful
- All documentation updated
- Monitoring and alerts configured
- Retrospective completed
Expected Deliverables
docs/
user-guides/
sso-setup.md (new)
mcp-token-generation.md (new)
claude-integration.md (new)
admin-guides/
tenant-management.md (new)
troubleshooting-sso.md (new)
monitoring.md (new)
reports/
2025-11-13-Post-Deployment-Report.md (new)
2025-11-13-Retrospective-Notes.md (new)
2025-11-13-M1.2-Final-Report.md (new)
Dependencies
- Day 9 deployment successful
- No critical issues in production
Risks
- Unexpected production issues (mitigation: rollback plan ready)
- User adoption issues (mitigation: clear documentation, training)
Dependencies and Critical Path
Critical Path Analysis
Critical Path: Day 1 → Day 2 → Day 3 → Day 4 → Day 9 (Backend-dependent path)
Day 1: Domain Layer (COMPLETE)
↓
Day 2: Infrastructure + TenantContext
↓
Day 3: Application Layer + APIs
↓
Day 4: Migration Prep + Testing
↓ (Backend Ready)
Day 5: Frontend Core (can start if APIs mocked)
↓
Day 6: Frontend Settings
↓
Day 7: Frontend MCP
↓ (Frontend Ready)
Day 8: Integration Testing
↓
Day 9: Production Migration
↓
Day 10: Validation
Parallel Work Opportunities
Days 5-7 (Frontend) can start in parallel with Days 2-4 (Backend) if:
- API contracts defined (DONE - API integration guide complete)
- MSW mocks configured for frontend development
- Backend APIs deployed to staging environment when ready
Optimization:
- Frontend team can start Day 5 tasks while backend completes Day 3
- This compresses timeline by 1-2 days if backend APIs are delayed
Dependencies Matrix
| Task | Depends On | Blocks |
|---|---|---|
| Day 1: Domain | - | Day 2 |
| Day 2: Infrastructure | Day 1 | Day 3 |
| Day 3: Application + APIs | Day 2 | Day 4, Day 5 (for real API testing) |
| Day 4: Migration Prep | Day 3 | Day 9 |
| Day 5: Frontend Core | API contracts (done), ideally Day 3 for real APIs | Day 6 |
| Day 6: Frontend Settings | Day 5 | Day 7 |
| Day 7: Frontend MCP | Day 6 | Day 8 |
| Day 8: Integration Testing | Days 4 + 7 | Day 9 |
| Day 9: Migration | Days 4 + 8 | Day 10 |
| Day 10: Validation | Day 9 | - |
Resource Allocation
Team Assignments
| Day | Backend | Frontend | QA | DevOps | DBA | PM |
|---|---|---|---|---|---|---|
| 1 | Full time (6h) | - | - | - | - | Review (1h) |
| 2 | Full time (5h) | - | - | - | - | Review (1h) |
| 3 | Full time (5h) | - | - | - | - | Review (1h) |
| 4 | Part time (3h) | - | - | - | Full time (5h) | Review (1h) |
| 5 | Support (1h) | Full time (8h) | - | - | - | Review (1h) |
| 6 | Support (1h) | Full time (7h) | - | - | - | Review (1h) |
| 7 | Support (1h) | Full time (8h) | - | - | - | Review (1h) |
| 8 | Part time (3h) | Part time (3h) | Full time (8h) | - | - | Review (2h) |
| 9 | Part time (3h) | - | Testing (4h) | Full time (8h) | Part time (4h) | Oversight (4h) |
| 10 | Support (2h) | Support (2h) | Testing (4h) | Monitoring (4h) | - | Reporting (6h) |
Total Effort:
- Backend Engineer: ~30 hours
- Frontend Engineer: ~31 hours
- QA Engineer: ~16 hours
- DevOps Engineer: ~12 hours
- DBA: ~9 hours
- Product Manager: ~16 hours
- Total: ~114 team-hours over 10 days
Risk Management
High-Risk Items
| Risk | Probability | Impact | Mitigation |
|---|---|---|---|
| Data loss during migration | Low | Critical | Full backup, tested rollback, validation scripts |
| Extended downtime | Medium | High | Pre-test migration, have rollback ready, schedule off-peak |
| Performance degradation | Medium | High | Performance testing on Day 4, proper indexes |
| Critical bugs found on Day 8 | Medium | High | Allow extra time on Day 9 for fixes |
| SSO integration issues | Low | Medium | Test with real IdPs, clear error messages |
Risk Mitigation Strategies
-
Technical Risks:
- Comprehensive testing (unit, integration, E2E, security)
- Code reviews (all PRs reviewed by at least one other developer)
- Performance testing before production (Day 4)
- Staging environment mirrors production
-
Schedule Risks:
- Buffer time built into Days 8-9 (can absorb 1-day delay)
- Frontend can start earlier if APIs mocked
- Rollback plan tested and ready
-
Quality Risks:
- TDD approach (tests written alongside code)
- Integration tests verify tenant isolation
- Security tests before production
- Code coverage target: >80%
Success Criteria
M1.2 Completion Criteria
- All 10 days complete
- All backend features implemented and tested
- All frontend features implemented and tested
- Database migration successful (no data loss)
- Production deployment successful
- All P0 and P1 bugs fixed
- Documentation complete (user guides + admin guides)
- Monitoring and alerts configured
- Stakeholder demo complete
Quality Metrics
| Metric | Target | Measurement Method |
|---|---|---|
| Test Coverage | >80% | Code coverage report |
| Unit Test Pass Rate | 100% | CI/CD pipeline |
| Integration Test Pass Rate | 100% | CI/CD pipeline |
| E2E Test Pass Rate | 100% | Playwright test report |
| API Response Time | <100ms (p95) | APM dashboard |
| Database Query Time | <50ms (p95) | pg_stat_statements |
| Error Rate | <1% | Sentry dashboard |
| Uptime | >99.9% | Status page |
Feature Completion Checklist
Multi-Tenancy:
- Tenant registration works (3-step wizard)
- Tenant isolation enforced (cross-tenant queries fail)
- Tenant context resolved from JWT claims
- Global Query Filter applies automatically
- Composite indexes improve performance
SSO Integration:
- OIDC login works (Azure AD, Google, Okta)
- SAML 2.0 login works (generic IdP)
- SSO configuration UI functional for admins
- User auto-provisioning works
- Email domain restrictions enforced
- SSO errors handled gracefully
MCP Authentication:
- MCP token generation works (3-step wizard)
- Token displayed once with warning
- Token authentication works (API calls)
- Fine-grained permissions enforced
- Token revocation works instantly
- Audit logs created for all operations
Communication Plan
Daily Standups
Time: 9:00 AM daily Duration: 15 minutes Attendees: All team members Format:
- What did you complete yesterday?
- What are you working on today?
- Any blockers?
Progress Updates
Frequency: End of each day Owner: Product Manager Format: Slack message with:
- Day summary (what was completed)
- Current status (on track / at risk / blocked)
- Next day plan
- Any issues or decisions needed
Milestone Reviews
Schedule:
- Day 4 (End of Backend phase): 1-hour review meeting
- Day 7 (End of Frontend phase): 1-hour review meeting
- Day 10 (End of M1.2): 2-hour retrospective
Stakeholder Updates
Frequency: Every 3 days Owner: Product Manager Audience: Executive team, stakeholders Format: Written update with:
- Progress summary
- Key achievements
- Risks and issues
- Next steps
Appendix A: File Count Summary
Expected Files Created
Backend (Days 1-4):
- Domain: 27 source files
- Application: ~20 files (Commands, Queries, Handlers, Validators)
- Infrastructure: ~15 files (Repositories, DbContext, Configurations)
- Tests: ~15 test files (~100 total tests)
- Total: ~77 files
Frontend (Days 5-7):
- Pages: ~10 files
- Components: ~20 files
- Hooks: ~15 files
- Services: ~5 files
- Stores: ~2 files
- Types: ~5 files
- Tests: ~30 test files (~150 total tests)
- Total: ~87 files
Documentation (Days 8-10):
- User guides: ~3 files
- Admin guides: ~3 files
- Reports: ~5 files
- Total: ~11 files
Overall: ~175 new files created
Appendix B: Testing Matrix
| Test Type | Count | Tool | Owner | When |
|---|---|---|---|---|
| Unit Tests (Backend) | ~80 | xUnit | Backend | Days 1-4 |
| Unit Tests (Frontend) | ~70 | Vitest | Frontend | Days 5-7 |
| Integration Tests (Backend) | ~30 | xUnit + TestContainers | Backend | Days 3-4 |
| Integration Tests (Frontend) | ~20 | React Testing Library | Frontend | Days 6-7 |
| E2E Tests | ~10 | Playwright | QA | Day 8 |
| Security Tests | ~8 | Custom + OWASP ZAP | QA | Day 8 |
| Performance Tests | ~5 | k6 | DevOps | Day 4, Day 8 |
| Total Tests | ~223 | - | All | Days 1-10 |
Plan Status: Active - In Execution Next Update: Day 2 Evening (2025-11-04) Contact: Product Manager for questions or updates
End of 10-Day Implementation Plan