Yaojia Wang ebb56cc9f8 feat(backend): Create Sprint 2 backend Stories and Tasks
Created detailed implementation plans for Sprint 2 backend work:

Story 1: Audit Log Foundation (Phase 1)
- Task 1: Design AuditLog database schema and create migration
- Task 2: Create AuditLog entity and Repository
- Task 3: Implement EF Core SaveChangesInterceptor
- Task 4: Write unit tests for audit logging
- Task 5: Integrate with ProjectManagement Module

Story 2: Audit Log Core Features (Phase 2)
- Task 1: Implement Changed Fields Detection (JSON Diff)
- Task 2: Integrate User Context Tracking
- Task 3: Add Multi-Tenant Isolation
- Task 4: Implement Audit Query API
- Task 5: Write Integration Tests

Story 3: Sprint Management Module
- Task 1: Create Sprint Aggregate Root and Domain Events
- Task 2: Implement Sprint Repository and EF Core Configuration
- Task 3: Create CQRS Commands and Queries
- Task 4: Implement Burndown Chart Calculation
- Task 5: Add SignalR Real-Time Notifications
- Task 6: Write Integration Tests

Total: 3 Stories, 16 Tasks, 24 Story Points (8+8+8)
Estimated Duration: 10-12 days

All tasks include:
- Detailed technical implementation guidance
- Code examples and file paths
- Testing requirements (>= 90% coverage)
- Performance benchmarks (< 5ms audit overhead)
- Multi-tenant security validation

🤖 Generated with [Claude Code](https://claude.com/claude-code)

Co-Authored-By: Claude <noreply@anthropic.com>
2025-11-04 22:56:31 +01:00

106 lines
3.4 KiB
Markdown

---
story_id: sprint_2_story_3
sprint: sprint_2
priority: P1
status: not_started
story_points: 8
estimated_days: 3-4
created_date: 2025-11-05
assignee: Backend Team
---
# Story 3: Sprint Management Module
**Sprint**: Sprint 2
**Priority**: P1 (Should Have)
**Estimated**: 3-4 days (Day 31-34)
**Owner**: Backend Team
## Description
Implement complete Sprint management functionality to support agile sprint planning, tracking, and burndown analytics. Enable teams to organize work into time-boxed iterations.
## Acceptance Criteria
- [ ] Sprint entity created with proper domain logic
- [ ] 9 CQRS API endpoints implemented (Create, Update, Delete, Get, List, Start, Complete, AddTask, RemoveTask)
- [ ] Burndown chart data calculation implemented
- [ ] SignalR real-time notifications for Sprint events
- [ ] Multi-tenant isolation enforced
- [ ] Integration tests with >= 90% coverage
- [ ] All tests passing
## Technical Requirements
**Sprint Entity**:
- Fields: `SprintId`, `TenantId`, `ProjectId`, `Name`, `Goal`, `StartDate`, `EndDate`, `Status` (Planned/Active/Completed)
- Relationships: `Project` (many-to-one), `Tasks` (one-to-many)
- Business Logic: Validate dates, status transitions, capacity tracking
**API Endpoints**:
1. POST /api/sprints - Create Sprint
2. PUT /api/sprints/{id} - Update Sprint
3. DELETE /api/sprints/{id} - Delete Sprint
4. GET /api/sprints/{id} - Get Sprint by ID
5. GET /api/sprints - List Sprints (with filters)
6. POST /api/sprints/{id}/start - Start Sprint
7. POST /api/sprints/{id}/complete - Complete Sprint
8. POST /api/sprints/{id}/tasks/{taskId} - Add Task to Sprint
9. DELETE /api/sprints/{id}/tasks/{taskId} - Remove Task from Sprint
**Burndown Chart**:
- Calculate remaining story points per day
- Track completed vs remaining work
- Return data for chart visualization
**Technology Stack**:
- Domain Layer: Sprint aggregate root + domain events
- Application Layer: CQRS (5 commands + 4 queries)
- Infrastructure Layer: PostgreSQL + EF Core
- Real-time: SignalR SprintHub
## Tasks
- [ ] [Task 1](sprint_2_story_3_task_1.md) - Create Sprint Aggregate Root and Domain Events
- [ ] [Task 2](sprint_2_story_3_task_2.md) - Implement Sprint Repository and EF Core Configuration
- [ ] [Task 3](sprint_2_story_3_task_3.md) - Create CQRS Commands and Queries
- [ ] [Task 4](sprint_2_story_3_task_4.md) - Implement Burndown Chart Calculation
- [ ] [Task 5](sprint_2_story_3_task_5.md) - Add SignalR Real-Time Notifications
- [ ] [Task 6](sprint_2_story_3_task_6.md) - Write Integration Tests
**Progress**: 0/6 tasks completed
## Dependencies
**Prerequisites**:
- ✅ ProjectManagement Module 95% Production Ready (Day 16)
- ✅ SignalR Backend 100% Complete (Day 17)
- ✅ Multi-Tenant Security Complete (Day 15)
## Definition of Done
- All 6 tasks completed
- 9 API endpoints working
- Burndown chart data calculation implemented
- SignalR notifications working
- All tests passing (>= 90% coverage)
- Multi-tenant isolation verified
- Code reviewed and approved
- Git commit created
## Notes
**Sprint Lifecycle**:
1. Planned → Active (Start Sprint)
2. Active → Completed (Complete Sprint)
3. Cannot delete Active sprint (must complete first)
**Burndown Chart Formula**:
- Total Story Points = Sum of all tasks in sprint
- Remaining Story Points = Sum of incomplete tasks
- Daily Burndown = [(Start Date, Total), ..., (Today, Remaining), ..., (End Date, 0 ideal)]
---
**Created**: 2025-11-05 by Backend Agent