Created detailed implementation plans for Sprint 2 backend work: Story 1: Audit Log Foundation (Phase 1) - Task 1: Design AuditLog database schema and create migration - Task 2: Create AuditLog entity and Repository - Task 3: Implement EF Core SaveChangesInterceptor - Task 4: Write unit tests for audit logging - Task 5: Integrate with ProjectManagement Module Story 2: Audit Log Core Features (Phase 2) - Task 1: Implement Changed Fields Detection (JSON Diff) - Task 2: Integrate User Context Tracking - Task 3: Add Multi-Tenant Isolation - Task 4: Implement Audit Query API - Task 5: Write Integration Tests Story 3: Sprint Management Module - Task 1: Create Sprint Aggregate Root and Domain Events - Task 2: Implement Sprint Repository and EF Core Configuration - Task 3: Create CQRS Commands and Queries - Task 4: Implement Burndown Chart Calculation - Task 5: Add SignalR Real-Time Notifications - Task 6: Write Integration Tests Total: 3 Stories, 16 Tasks, 24 Story Points (8+8+8) Estimated Duration: 10-12 days All tasks include: - Detailed technical implementation guidance - Code examples and file paths - Testing requirements (>= 90% coverage) - Performance benchmarks (< 5ms audit overhead) - Multi-tenant security validation 🤖 Generated with [Claude Code](https://claude.com/claude-code) Co-Authored-By: Claude <noreply@anthropic.com>
3.4 KiB
3.4 KiB
story_id, sprint, priority, status, story_points, estimated_days, created_date, assignee
| story_id | sprint | priority | status | story_points | estimated_days | created_date | assignee |
|---|---|---|---|---|---|---|---|
| sprint_2_story_3 | sprint_2 | P1 | not_started | 8 | 3-4 | 2025-11-05 | Backend Team |
Story 3: Sprint Management Module
Sprint: Sprint 2 Priority: P1 (Should Have) Estimated: 3-4 days (Day 31-34) Owner: Backend Team
Description
Implement complete Sprint management functionality to support agile sprint planning, tracking, and burndown analytics. Enable teams to organize work into time-boxed iterations.
Acceptance Criteria
- Sprint entity created with proper domain logic
- 9 CQRS API endpoints implemented (Create, Update, Delete, Get, List, Start, Complete, AddTask, RemoveTask)
- Burndown chart data calculation implemented
- SignalR real-time notifications for Sprint events
- Multi-tenant isolation enforced
- Integration tests with >= 90% coverage
- All tests passing
Technical Requirements
Sprint Entity:
- Fields:
SprintId,TenantId,ProjectId,Name,Goal,StartDate,EndDate,Status(Planned/Active/Completed) - Relationships:
Project(many-to-one),Tasks(one-to-many) - Business Logic: Validate dates, status transitions, capacity tracking
API Endpoints:
- POST /api/sprints - Create Sprint
- PUT /api/sprints/{id} - Update Sprint
- DELETE /api/sprints/{id} - Delete Sprint
- GET /api/sprints/{id} - Get Sprint by ID
- GET /api/sprints - List Sprints (with filters)
- POST /api/sprints/{id}/start - Start Sprint
- POST /api/sprints/{id}/complete - Complete Sprint
- POST /api/sprints/{id}/tasks/{taskId} - Add Task to Sprint
- DELETE /api/sprints/{id}/tasks/{taskId} - Remove Task from Sprint
Burndown Chart:
- Calculate remaining story points per day
- Track completed vs remaining work
- Return data for chart visualization
Technology Stack:
- Domain Layer: Sprint aggregate root + domain events
- Application Layer: CQRS (5 commands + 4 queries)
- Infrastructure Layer: PostgreSQL + EF Core
- Real-time: SignalR SprintHub
Tasks
- Task 1 - Create Sprint Aggregate Root and Domain Events
- Task 2 - Implement Sprint Repository and EF Core Configuration
- Task 3 - Create CQRS Commands and Queries
- Task 4 - Implement Burndown Chart Calculation
- Task 5 - Add SignalR Real-Time Notifications
- Task 6 - Write Integration Tests
Progress: 0/6 tasks completed
Dependencies
Prerequisites:
- ✅ ProjectManagement Module 95% Production Ready (Day 16)
- ✅ SignalR Backend 100% Complete (Day 17)
- ✅ Multi-Tenant Security Complete (Day 15)
Definition of Done
- All 6 tasks completed
- 9 API endpoints working
- Burndown chart data calculation implemented
- SignalR notifications working
- All tests passing (>= 90% coverage)
- Multi-tenant isolation verified
- Code reviewed and approved
- Git commit created
Notes
Sprint Lifecycle:
- Planned → Active (Start Sprint)
- Active → Completed (Complete Sprint)
- Cannot delete Active sprint (must complete first)
Burndown Chart Formula:
- Total Story Points = Sum of all tasks in sprint
- Remaining Story Points = Sum of incomplete tasks
- Daily Burndown = [(Start Date, Total), ..., (Today, Remaining), ..., (End Date, 0 ideal)]
Created: 2025-11-05 by Backend Agent