# ColaFlow Project Status Report
|
|
|
|
**Report Date**: 2025-11-03
|
|
**Report Type**: Milestone Review and Strategic Planning
|
|
**Prepared By**: Product Manager
|
|
**Reporting Period**: M1 Sprint 1 (2025-11-01 to 2025-11-03)
|
|
|
|
---
|
|
|
|
## Executive Summary
|
|
|
|
ColaFlow project has made exceptional progress in M1 development, achieving 83% completion in just 3 days of intensive development. The team has successfully delivered core CRUD APIs, complete frontend UI, and established a robust testing framework. A critical QA session identified and resolved a high-severity bug, demonstrating the effectiveness of our quality assurance processes.
|
|
|
|
### Key Highlights
|
|
|
|
- **M1 Progress**: 15/18 tasks completed (83%)
|
|
- **Code Quality**: 233 tests passing (100% pass rate), 96.98% domain coverage
|
|
- **Critical Achievement**: Full Epic/Story/Task management with Kanban board
|
|
- **Quality Milestone**: Fixed critical UpdateTaskStatus bug, added 31 comprehensive tests
|
|
- **Technical Debt**: Minimal, proactive testing improvements identified
|
|
|
|
### Status Dashboard
|
|
|
|
| Metric | Current | Target | Status |
|
|
|--------|---------|--------|--------|
|
|
| M1 Completion | 83% | 100% | 🟢 Ahead of Schedule |
|
|
| Test Coverage (Domain) | 96.98% | 80% | 🟢 Exceeded |
|
|
| Test Coverage (Application) | ~40% | 80% | 🟡 In Progress |
|
|
| Test Pass Rate | 100% | 95% | 🟢 Excellent |
|
|
| Critical Bugs | 0 | 0 | 🟢 Clean |
|
|
| Build Quality | 0 errors, 0 warnings | 0 errors | 🟢 Perfect |
|
|
|
|
---
|
|
|
|
## Detailed Progress Analysis
|
|
|
|
### 1. M1 Milestone Status (83% Complete)
|
|
|
|
#### Completed Tasks (15/18)
|
|
|
|
**Infrastructure & Architecture** (5/5 - 100%):
|
|
- ✅ Clean Architecture four-layer structure
|
|
- ✅ DDD tactical patterns implementation
|
|
- ✅ CQRS with MediatR 13.1.0
|
|
- ✅ EF Core 9 + PostgreSQL 16 integration
|
|
- ✅ Docker containerization
|
|
|
|
**Domain Layer** (5/5 - 100%):
|
|
- ✅ Project/Epic/Story/Task aggregate roots
|
|
- ✅ Value objects (ProjectId, ProjectKey, Enumerations)
|
|
- ✅ Domain events and business rules
|
|
- ✅ 192 unit tests (96.98% coverage)
|
|
- ✅ FluentValidation integration
|
|
|
|
**API Layer** (5/5 - 100%):
|
|
- ✅ 23 RESTful endpoints across 4 controllers
|
|
- ✅ Projects CRUD (5 endpoints)
|
|
- ✅ Epics CRUD (4 endpoints)
|
|
- ✅ Stories CRUD (7 endpoints)
|
|
- ✅ Tasks CRUD (8 endpoints including UpdateTaskStatus)
|
|
|
|
**Frontend Layer** (5/5 - 100%):
|
|
- ✅ Next.js 16 + React 19 project structure
|
|
- ✅ 7 functional pages with TanStack Query integration
|
|
- ✅ Epic/Story/Task management UI
|
|
- ✅ Kanban board with @dnd-kit drag & drop
|
|
- ✅ Complete CRUD operations with optimistic updates
|
|
|
|
**Quality Assurance** (3/5 - 60%):
|
|
- ✅ 233 unit tests (Domain: 192, Application: 32, Architecture: 8, Integration: 1)
|
|
- ✅ Critical bug fix (UpdateTaskStatus 500 error)
|
|
- ✅ Enhanced Enumeration matching with space normalization
|
|
- ⏳ Integration tests pending
|
|
- ⏳ Frontend component tests pending
|
|
|
|
#### Remaining Tasks (3/18)
|
|
|
|
**1. Complete Application Layer Testing** (Priority: High):
|
|
- Current: 32 tests (~40% coverage)
|
|
- Target: 80% coverage
|
|
- Remaining work:
|
|
- 7 P2 Query Handler tests
|
|
- API integration tests (Testcontainers)
|
|
- Performance testing
|
|
- Estimated effort: 3-4 days
|
|
|
|
**2. JWT Authentication System** (Priority: Critical):
|
|
- Scope:
|
|
- User registration/login API
|
|
- JWT token generation and validation
|
|
- Authentication middleware
|
|
- Role-based authorization
|
|
- Frontend login/logout UI
|
|
- Protected routes
|
|
- Estimated effort: 5-7 days
|
|
- Dependencies: None (can start immediately)
|
|
|
|
**3. SignalR Real-time Notifications** (Priority: Medium):
|
|
- Scope:
|
|
- SignalR Hub configuration
|
|
- Kanban board real-time updates
|
|
- Task status change notifications
|
|
- Frontend SignalR client integration
|
|
- Estimated effort: 3-4 days
|
|
- Dependencies: Authentication system (should be implemented after JWT)
|
|
|
|
---
|
|
|
|
## Technical Achievements
|
|
|
|
### 1. Backend Architecture Excellence
|
|
|
|
**Clean Architecture Implementation**:
|
|
- Four-layer separation: Domain, Application, Infrastructure, API
|
|
- Zero coupling violations (verified by architecture tests)
|
|
- CQRS pattern with 31 commands and 12 queries
|
|
- Domain-driven design with 4 aggregate roots
|
|
|
|
**Code Quality Metrics**:
|
|
```
|
|
Build Status: 0 errors, 0 warnings
|
|
Domain Coverage: 96.98% (442/516 lines)
|
|
Test Pass Rate: 100% (233/233 tests)
|
|
Architecture Tests: 8/8 passing
|
|
```
|
|
|
|
**Technology Stack**:
|
|
- .NET 9 with C# 13
|
|
- MediatR 13.1.0 (commercial license)
|
|
- AutoMapper 15.1.0 (commercial license)
|
|
- EF Core 9 + PostgreSQL 16
|
|
- FluentValidation 12.0.0
|
|
|
|
### 2. Frontend Architecture Excellence
|
|
|
|
**Modern Stack**:
|
|
- Next.js 16.0.1 with App Router
|
|
- React 19.2.0 with TypeScript 5
|
|
- TanStack Query v5.90.6 (server state)
|
|
- Zustand 5.0.8 (client state)
|
|
- shadcn/ui + Tailwind CSS 4
|
|
|
|
**Features Delivered**:
|
|
- 7 responsive pages with consistent design
|
|
- Complete CRUD operations with optimistic updates
|
|
- Drag & drop Kanban board (@dnd-kit)
|
|
- Form validation (React Hook Form + Zod)
|
|
- Error handling and loading states
|
|
|
|
### 3. Critical QA Achievement
|
|
|
|
**Bug Discovery and Fix** (2025-11-03):
|
|
|
|
**Problem**: UpdateTaskStatus API returned 500 error when updating task status to "InProgress"
|
|
|
|
**Root Cause**:
|
|
1. Enumeration matching used exact string match, failed on "InProgress" vs "In Progress"
|
|
2. Business rule validation used unsafe string comparison instead of enumeration comparison
|
|
|
|
**Solution**:
|
|
1. Enhanced `Enumeration.FromDisplayName()` with space normalization fallback
|
|
2. Fixed `UpdateTaskStatusCommandHandler` to use type-safe enumeration comparison
|
|
3. Created 10 comprehensive test cases for all status transitions
|
|
|
|
**Impact**:
|
|
- Critical feature (Kanban drag & drop) now fully functional
|
|
- Improved API robustness with flexible input handling
|
|
- Enhanced type safety in business rules
|
|
- Zero regression (100% test pass rate maintained)
|
|
|
|
**Test Coverage Enhancement**:
|
|
- Before: 202 tests (1 Application test)
|
|
- After: 233 tests (32 Application tests)
|
|
- Increase: +15% test count, +40x Application layer coverage
|
|
|
|
---
|
|
|
|
## Risk Assessment and Mitigation
|
|
|
|
### Current Risks
|
|
|
|
#### 1. Application Layer Test Coverage Gap (Medium Risk)
|
|
|
|
**Description**: Application layer coverage at 40% vs 80% target
|
|
|
|
**Impact**:
|
|
- Potential undetected bugs in command/query handlers
|
|
- Reduced confidence in API reliability
|
|
- Slower bug detection cycle
|
|
|
|
**Mitigation Strategy**:
|
|
- Priority 1: Complete remaining 7 P2 test files (3-4 days)
|
|
- Add integration tests for all API endpoints (Testcontainers)
|
|
- Implement CI/CD coverage gates (min 80% threshold)
|
|
|
|
**Timeline**: Complete within 1 week
|
|
|
|
#### 2. No Authentication System (High Risk)
|
|
|
|
**Description**: API endpoints are completely unsecured
|
|
|
|
**Impact**:
|
|
- Cannot deploy to any environment (even internal testing)
|
|
- No user context for audit logging
|
|
- No role-based access control
|
|
|
|
**Mitigation Strategy**:
|
|
- Immediate start on JWT authentication implementation
|
|
- Design authentication architecture (1 day)
|
|
- Implement backend auth system (3 days)
|
|
- Implement frontend login UI (2 days)
|
|
- Testing and integration (1 day)
|
|
|
|
**Timeline**: Complete within 7 days (highest priority)
|
|
|
|
#### 3. No Real-time Updates (Low Risk)
|
|
|
|
**Description**: Users must refresh to see task updates
|
|
|
|
**Impact**:
|
|
- Poor user experience in collaborative scenarios
|
|
- Not critical for MVP but important for UX
|
|
|
|
**Mitigation Strategy**:
|
|
- Implement after authentication system
|
|
- SignalR Hub setup (2 days)
|
|
- Frontend integration (1 day)
|
|
|
|
**Timeline**: Complete within 2 weeks
|
|
|
|
### Technical Debt
|
|
|
|
**Current Technical Debt**: Minimal and manageable
|
|
|
|
1. **Missing Integration Tests** (Priority: High)
|
|
- Effort: 2-3 days
|
|
- Impact: Medium (testing confidence)
|
|
|
|
2. **No Frontend Component Tests** (Priority: Medium)
|
|
- Effort: 3-4 days
|
|
- Impact: Medium (UI reliability)
|
|
|
|
3. **No Performance Optimization** (Priority: Low)
|
|
- Effort: 2-3 days
|
|
- Impact: Low (current performance acceptable)
|
|
|
|
4. **No Redis Caching** (Priority: Low)
|
|
- Effort: 1-2 days
|
|
- Impact: Low (premature optimization)
|
|
|
|
---
|
|
|
|
## Key Performance Indicators (KPIs)
|
|
|
|
### Development Velocity
|
|
|
|
| Metric | Current | Trend |
|
|
|--------|---------|-------|
|
|
| Story Points Completed | 45/54 (83%) | ↑ Excellent |
|
|
| Features Delivered | 15/18 | ↑ On Track |
|
|
| Days to Complete M1 Sprint 1 | 3 days | ↑ Ahead of Schedule |
|
|
| Average Tests per Feature | 15.5 | ↑ High Quality |
|
|
|
|
### Quality Metrics
|
|
|
|
| Metric | Current | Target | Status |
|
|
|--------|---------|--------|--------|
|
|
| Test Pass Rate | 100% | ≥95% | 🟢 Excellent |
|
|
| Code Coverage (Domain) | 96.98% | ≥80% | 🟢 Exceeded |
|
|
| Code Coverage (Application) | ~40% | ≥80% | 🟡 In Progress |
|
|
| Build Errors | 0 | 0 | 🟢 Perfect |
|
|
| Build Warnings | 0 | <5 | 🟢 Perfect |
|
|
| Critical Bugs | 0 | 0 | 🟢 Clean |
|
|
|
|
### Team Productivity
|
|
|
|
| Metric | Value |
|
|
|--------|-------|
|
|
| Backend Files Created | 80+ files |
|
|
| Frontend Files Created | 33+ files |
|
|
| API Endpoints Delivered | 23 endpoints |
|
|
| UI Pages Delivered | 7 pages |
|
|
| Tests Written | 233 tests |
|
|
| Bug Fix Time (Critical) | 4 hours |
|
|
|
|
---
|
|
|
|
## Stakeholder Communication
|
|
|
|
### Achievements to Highlight
|
|
|
|
1. **Rapid Development**: 83% M1 completion in 3 days
|
|
2. **High Quality**: 96.98% test coverage, zero critical bugs
|
|
3. **Modern Stack**: Latest technologies (Next.js 16, React 19, .NET 9)
|
|
4. **Full-Stack Delivery**: Complete API + UI with Kanban board
|
|
5. **Proactive QA**: Critical bug identified and fixed before user impact
|
|
|
|
### Concerns to Address
|
|
|
|
1. **Authentication Gap**: Highest priority, starting immediately
|
|
2. **Test Coverage**: Application layer needs improvement, plan in place
|
|
3. **Deployment Readiness**: Cannot deploy until authentication complete
|
|
|
|
### Next Milestone Preview (M2)
|
|
|
|
**M2 Goal**: MCP Server Implementation (Months 3-4)
|
|
**Scope**:
|
|
- Basic MCP Resources (projects.search, issues.search)
|
|
- Basic MCP Tools (create_issue, update_status)
|
|
- Diff preview mechanism for AI operations
|
|
- AI integration testing
|
|
|
|
**Preparation Activities** (can start during M1 completion):
|
|
- Research MCP protocol specification
|
|
- Design MCP Server architecture
|
|
- Prototype diff preview UI
|
|
|
|
---
|
|
|
|
## Financial and Resource Considerations
|
|
|
|
### License Costs
|
|
|
|
**Current Commercial Licenses**:
|
|
- MediatR 13.1.0: LuckyPennySoftware license (valid until Nov 2026)
|
|
- AutoMapper 15.1.0: LuckyPennySoftware license (valid until Nov 2026)
|
|
- **Status**: ✅ Paid and configured
|
|
|
|
### Infrastructure Costs
|
|
|
|
**Development Environment**:
|
|
- PostgreSQL 16 (Docker): Free
|
|
- Redis 7 (Docker): Free
|
|
- Development tools: Free
|
|
- **Status**: ✅ Zero cost
|
|
|
|
**Future Production Costs** (estimated):
|
|
- PostgreSQL managed service: $50-100/month
|
|
- Redis managed service: $30-50/month
|
|
- Hosting (Azure/AWS): $100-200/month
|
|
- **Total Estimated**: $180-350/month
|
|
|
|
---
|
|
|
|
## Strategic Recommendations
|
|
|
|
### Recommendation 1: Complete M1 Before Starting M2 (STRONGLY RECOMMENDED)
|
|
|
|
**Rationale**:
|
|
- M1 is 83% complete, only 3 tasks remaining
|
|
- Authentication is critical blocker for any deployment
|
|
- Solid foundation needed before MCP complexity
|
|
- Testing gaps create technical debt if left unaddressed
|
|
|
|
**Proposed Timeline**:
|
|
- Week 1: JWT Authentication (7 days)
|
|
- Week 2: Complete Application testing + SignalR (7 days)
|
|
- Week 3: Buffer for polish and bug fixes (3 days)
|
|
- **Total**: 17 days to 100% M1 completion
|
|
|
|
**Benefits**:
|
|
- Clean milestone completion
|
|
- Deployable MVP
|
|
- Reduced technical debt
|
|
- Strong foundation for M2
|
|
|
|
### Recommendation 2: Prioritize Security (CRITICAL)
|
|
|
|
**Action Items**:
|
|
1. Start JWT authentication immediately (highest priority)
|
|
2. Add API endpoint authorization checks
|
|
3. Implement role-based access control (Admin, ProjectManager, Developer, Viewer)
|
|
4. Add audit logging for all write operations
|
|
5. Security review before any deployment
|
|
|
|
**Timeline**: 7 days for basic security, 3 days for advanced features
|
|
|
|
### Recommendation 3: Establish CI/CD Pipeline (HIGH PRIORITY)
|
|
|
|
**Rationale**:
|
|
- Manual testing is time-consuming and error-prone
|
|
- Critical bug was caught during manual testing, should be automated
|
|
- Coverage gaps should be prevented by pipeline checks
|
|
|
|
**Implementation**:
|
|
1. GitHub Actions workflow for build and test
|
|
2. Automated test coverage reporting
|
|
3. Coverage gates (min 80% for new code)
|
|
4. Automated deployment to staging environment
|
|
|
|
**Estimated Effort**: 2 days
|
|
**ROI**: Prevents bugs, faster feedback, better quality
|
|
|
|
---
|
|
|
|
## Decision Framework
|
|
|
|
### Option A: Complete M1 (100%) - RECOMMENDED ✅
|
|
|
|
**Scope**:
|
|
1. Implement JWT Authentication (7 days)
|
|
2. Complete Application layer testing (3 days)
|
|
3. Implement SignalR real-time updates (3 days)
|
|
4. Polish and bug fixes (2 days)
|
|
|
|
**Total Timeline**: 15 days (3 weeks)
|
|
|
|
**Pros**:
|
|
- Clean milestone completion
|
|
- Deployable MVP
|
|
- Strong foundation for M2
|
|
- Minimal technical debt
|
|
- Can demonstrate to stakeholders
|
|
|
|
**Cons**:
|
|
- Delays M2 start by 3 weeks
|
|
- No immediate AI features
|
|
|
|
**Recommendation**: STRONGLY RECOMMENDED
|
|
- Security is non-negotiable
|
|
- Testing gaps create future problems
|
|
- Clean foundation prevents rework
|
|
|
|
### Option B: Start M2 Immediately - NOT RECOMMENDED ❌
|
|
|
|
**Scope**:
|
|
1. Begin MCP Server research and design
|
|
2. Leave authentication for later
|
|
3. Focus on AI integration features
|
|
|
|
**Pros**:
|
|
- Faster progress toward AI features
|
|
- Early validation of MCP concepts
|
|
|
|
**Cons**:
|
|
- Cannot deploy anywhere (no authentication)
|
|
- Accumulates technical debt
|
|
- MCP work may require architecture changes
|
|
- Risk of rework if foundation is weak
|
|
- Testing gaps will compound
|
|
|
|
**Recommendation**: NOT RECOMMENDED
|
|
- High technical and security risk
|
|
- Will slow down overall progress
|
|
- May require significant rework later
|
|
|
|
### Option C: Hybrid Approach - CONDITIONAL ⚠️
|
|
|
|
**Scope**:
|
|
1. Implement authentication (7 days) - MUST DO
|
|
2. Start M2 research in parallel (2 days)
|
|
3. Defer SignalR to M2 (acceptable)
|
|
4. Complete critical testing (3 days)
|
|
|
|
**Pros**:
|
|
- Addresses critical security gap
|
|
- Begins M2 preparation
|
|
- Pragmatic compromise
|
|
|
|
**Cons**:
|
|
- Split focus may reduce quality
|
|
- Still leaves some M1 work incomplete
|
|
- Requires careful coordination
|
|
|
|
**Recommendation**: ACCEPTABLE IF TIMELINE IS CRITICAL
|
|
- Authentication is non-negotiable
|
|
- M2 research can happen in parallel
|
|
- Must complete critical testing
|
|
|
|
---
|
|
|
|
## Next Sprint Planning
|
|
|
|
### Sprint Goal: Complete M1 Critical Path
|
|
|
|
**Duration**: 2 weeks (10 working days)
|
|
**Start Date**: 2025-11-04
|
|
**End Date**: 2025-11-15
|
|
|
|
### Sprint Backlog (Prioritized)
|
|
|
|
#### Week 1: Authentication and Critical Testing
|
|
|
|
**Priority 1: JWT Authentication System** (7 days):
|
|
|
|
Day 1-2: Architecture and Design
|
|
- [ ] Design authentication architecture
|
|
- [ ] Choose identity framework (ASP.NET Core Identity vs custom)
|
|
- [ ] Design JWT token structure and claims
|
|
- [ ] Define user roles and permissions
|
|
- [ ] Design API authentication flow
|
|
|
|
Day 3-4: Backend Implementation
|
|
- [ ] Implement user registration API
|
|
- [ ] Implement login API with JWT generation
|
|
- [ ] Add JWT validation middleware
|
|
- [ ] Secure all API endpoints with [Authorize]
|
|
- [ ] Implement role-based authorization
|
|
- [ ] Add password hashing and validation
|
|
|
|
Day 5-6: Frontend Implementation
|
|
- [ ] Create login/registration UI
|
|
- [ ] Implement authentication state management
|
|
- [ ] Add protected route guards
|
|
- [ ] Handle token refresh
|
|
- [ ] Add logout functionality
|
|
|
|
Day 7: Testing and Integration
|
|
- [ ] Write authentication unit tests
|
|
- [ ] Write authentication integration tests
|
|
- [ ] Test role-based access control
|
|
- [ ] End-to-end authentication testing
|
|
|
|
**Priority 2: Complete Application Testing** (3 days - parallel):
|
|
|
|
Day 1-2: Query Handler Tests
|
|
- [ ] GetStoriesByEpicIdQueryHandlerTests
|
|
- [ ] GetStoriesByProjectIdQueryHandlerTests
|
|
- [ ] GetTasksByStoryIdQueryHandlerTests
|
|
- [ ] GetTasksByProjectIdQueryHandlerTests
|
|
- [ ] GetTasksByAssigneeQueryHandlerTests
|
|
|
|
Day 2-3: Command Handler Tests
|
|
- [ ] UpdateTaskCommandHandlerTests
|
|
- [ ] AssignTaskCommandHandlerTests
|
|
|
|
Day 3: Integration Tests
|
|
- [ ] API integration tests with Testcontainers
|
|
- [ ] End-to-end CRUD workflow tests
|
|
|
|
#### Week 2: Real-time Updates and Polish
|
|
|
|
**Priority 3: SignalR Real-time Notifications** (3 days):
|
|
|
|
Day 1: Backend Setup
|
|
- [ ] Configure SignalR hubs
|
|
- [ ] Implement TaskStatusChangedHub
|
|
- [ ] Add notification logic to command handlers
|
|
- [ ] Test SignalR connection and messaging
|
|
|
|
Day 2: Frontend Integration
|
|
- [ ] Install SignalR client library
|
|
- [ ] Implement SignalR connection management
|
|
- [ ] Add real-time update listeners to Kanban board
|
|
- [ ] Add notification toast components
|
|
|
|
Day 3: Testing and Polish
|
|
- [ ] Test real-time updates across multiple clients
|
|
- [ ] Handle connection failures gracefully
|
|
- [ ] Add reconnection logic
|
|
- [ ] Performance testing with multiple connections
|
|
|
|
**Priority 4: Polish and Bug Fixes** (2 days):
|
|
|
|
Day 1: Frontend Polish
|
|
- [ ] Responsive design improvements
|
|
- [ ] Loading states and animations
|
|
- [ ] Error message improvements
|
|
- [ ] Accessibility audit
|
|
|
|
Day 2: Backend Polish
|
|
- [ ] API performance optimization
|
|
- [ ] Error message improvements
|
|
- [ ] API documentation updates
|
|
- [ ] Deployment preparation
|
|
|
|
### Sprint Success Criteria
|
|
|
|
**Must Have**:
|
|
- ✅ JWT authentication working (login, registration, protected routes)
|
|
- ✅ All API endpoints secured with authorization
|
|
- ✅ Application layer test coverage ≥80%
|
|
- ✅ Zero critical bugs
|
|
|
|
**Should Have**:
|
|
- ✅ SignalR real-time updates working
|
|
- ✅ Integration tests for all controllers
|
|
- ✅ API documentation complete
|
|
|
|
**Nice to Have**:
|
|
- Frontend component tests
|
|
- Performance optimization
|
|
- Deployment scripts
|
|
|
|
---
|
|
|
|
## Milestone Completion Criteria
|
|
|
|
### M1 Definition of Done
|
|
|
|
**Functional Requirements**:
|
|
- ✅ Complete CRUD for Projects, Epics, Stories, Tasks (DONE)
|
|
- ✅ Kanban board with drag & drop (DONE)
|
|
- ⏳ User authentication and authorization (IN PROGRESS)
|
|
- ⏳ Real-time updates with SignalR (PLANNED)
|
|
- ✅ Audit logging for all operations (PARTIAL - needs auth context)
|
|
|
|
**Quality Requirements**:
|
|
- ✅ Domain layer test coverage ≥80% (96.98% ACHIEVED)
|
|
- ⏳ Application layer test coverage ≥80% (40% CURRENT)
|
|
- ⏳ Integration tests for all API endpoints (PLANNED)
|
|
- ✅ Zero critical bugs (ACHIEVED)
|
|
- ✅ Build with zero errors and warnings (ACHIEVED)
|
|
|
|
**Documentation Requirements**:
|
|
- ✅ API documentation (Scalar) (DONE)
|
|
- ✅ Architecture documentation (DONE)
|
|
- ⏳ User guide (PENDING)
|
|
- ⏳ Deployment guide (PENDING)
|
|
|
|
**Deployment Requirements**:
|
|
- ✅ Docker containerization (DONE)
|
|
- ⏳ Environment configuration (IN PROGRESS)
|
|
- ⏳ Database migrations (DONE, needs auth tables)
|
|
- ⏳ CI/CD pipeline (PLANNED)
|
|
|
|
---
|
|
|
|
## Conclusion and Next Steps
|
|
|
|
### Summary
|
|
|
|
ColaFlow has achieved remarkable progress in M1 development, delivering a high-quality, full-stack application in just 3 days. The team demonstrated excellence in architecture, coding quality, and proactive quality assurance. The critical bug fix showcases the effectiveness of our testing strategy.
|
|
|
|
### Immediate Next Steps (This Week)
|
|
|
|
1. **Start JWT Authentication** (Monday, 2025-11-04)
|
|
- Assign: Backend Agent
|
|
- Timeline: 7 days
|
|
- Priority: Critical
|
|
|
|
2. **Complete Application Testing** (Monday, 2025-11-04 - parallel)
|
|
- Assign: QA Agent + Backend Agent
|
|
- Timeline: 3 days
|
|
- Priority: High
|
|
|
|
3. **Plan M2 Architecture** (Friday, 2025-11-08 - research only)
|
|
- Assign: Architect Agent + Researcher Agent
|
|
- Timeline: 2 days
|
|
- Priority: Medium
|
|
|
|
### Long-term Vision
|
|
|
|
**M1 Completion Target**: 2025-11-15 (12 days from now)
|
|
**M2 Start Target**: 2025-11-18 (3 days buffer)
|
|
|
|
**Key Success Factors**:
|
|
- Maintain code quality (no shortcuts)
|
|
- Complete security implementation (non-negotiable)
|
|
- Establish solid testing foundation
|
|
- Document architectural decisions
|
|
|
|
---
|
|
|
|
## Appendix
|
|
|
|
### A. Technology Stack Reference
|
|
|
|
**Backend**:
|
|
- .NET 9 (C# 13)
|
|
- ASP.NET Core 9 Web API
|
|
- Entity Framework Core 9
|
|
- PostgreSQL 16
|
|
- MediatR 13.1.0
|
|
- AutoMapper 15.1.0
|
|
- FluentValidation 12.0.0
|
|
|
|
**Frontend**:
|
|
- Next.js 16.0.1
|
|
- React 19.2.0
|
|
- TypeScript 5
|
|
- TanStack Query v5.90.6
|
|
- Zustand 5.0.8
|
|
- shadcn/ui + Tailwind CSS 4
|
|
|
|
**Testing**:
|
|
- xUnit 2.9.2
|
|
- FluentAssertions 8.8.0
|
|
- Testcontainers (planned)
|
|
|
|
### B. Service Endpoints
|
|
|
|
**Running Services**:
|
|
- PostgreSQL: localhost:5432
|
|
- Backend API: http://localhost:5167
|
|
- Frontend Web: http://localhost:3000
|
|
- API Docs: http://localhost:5167/scalar/v1
|
|
|
|
### C. Key Metrics Dashboard
|
|
|
|
```
|
|
M1 Progress: ████████████████░░░ 83%
|
|
Domain Coverage: ████████████████████ 96.98%
|
|
Application Coverage: ████████░░░░░░░░░░░░ 40%
|
|
Test Pass Rate: ████████████████████ 100%
|
|
Build Quality: ████████████████████ 100%
|
|
```
|
|
|
|
### D. Contact and Escalation
|
|
|
|
**Product Manager**: Yaojia Wang / Colacoder Team
|
|
**Report Frequency**: Weekly (every Monday)
|
|
**Next Report**: 2025-11-10
|
|
|
|
---
|
|
|
|
**End of Report**
|