story_id, sprint_id, parent_story_id, status, priority, assignee, created_date, estimated_days, phase
story_id sprint_id parent_story_id status priority assignee created_date estimated_days phase
story_17 sprint_5 story_0 not_started P0 backend 2025-11-09 10 5

Story 17: Testing, Optimization & Documentation

Parent Epic: Story 0 - Integrate Microsoft .NET MCP SDK Phase: 5 - Testing & Optimization (Week 7-8) Priority: P0 - Critical Estimated Effort: 10 days (2 weeks) Dependencies: Story 16 (Transport migration complete)

User Story

As a backend team lead, I want comprehensive testing, performance optimization, and documentation for MCP SDK integration, So that we have production-ready code with zero regressions and complete knowledge transfer.

Business Value

  • Quality Assurance: Zero CRITICAL bugs in production
  • Performance Validation: Confirm ≥20% improvement target met
  • Security Confidence: Pass security audit with zero HIGH vulnerabilities
  • Team Knowledge: Complete documentation for future maintenance
  • Production Ready: Confident deployment with rollback plan

Week 7: Integration Testing & Bug Fixes

7.1 End-to-End Integration Testing (2 days)

Test Scenarios:

  1. Claude Desktop Integration (stdio)

    • Initialize handshake
    • List Tools and Resources
    • Call each Tool (10 total)
    • Query each Resource (11 total)
    • Verify Diff Preview workflow
    • Test approval/rejection flow
  2. Web Client Integration (HTTP/SSE)

    • HTTP POST requests to MCP endpoints
    • SSE connection for notifications
    • API Key authentication
    • CORS preflight handling
  3. Multi-Tenant Isolation

    • Create 2 test tenants
    • Verify cross-tenant data access blocked
    • Test API Keys scoped to tenants
    • Validate Global Query Filters
  4. Error Handling

    • Invalid API Key
    • Missing required parameters
    • Malformed JSON-RPC requests
    • Network failures (timeout, disconnect)

Deliverables:

  • Integration test suite (50+ test cases)
  • Test execution report
  • Bug tracking spreadsheet

7.2 Performance Testing & Optimization (2 days)

Baseline vs. Target Performance:

Metric Baseline (Custom) Target (SDK) Actual (Measured)
Tool Execution (P95) 150ms 120ms (20% faster) TBD
Resource Query (P95) 120ms 85ms (30% faster) TBD
Throughput 70 req/s 100 req/s TBD
Memory Usage 180 MB 150 MB (15% less) TBD

Performance Tests:

  1. Load Testing (Apache Bench or k6)

    • 100 concurrent users
    • 1000 requests total
    • Measure P50, P95, P99 latency
  2. Memory Profiling (dotMemory)

    • Baseline memory usage
    • Peak memory under load
    • Memory leak detection
  3. Database Query Performance

    • EF Core query analysis
    • Index usage verification
    • N+1 query detection

Optimization Tasks (if needed):

  • Add missing database indexes
  • Optimize Redis cache keys
  • Tune connection pool sizes
  • Enable HTTP response compression

Deliverables:

  • Performance benchmark report
  • Optimization recommendations
  • Before/after comparison charts

7.3 Security Audit (1 day)

Security Tests:

  1. Authentication & Authorization

    • API Key brute force attempt (rate limiting)
    • Expired API Key handling
    • Invalid API Key handling
    • Field-level permission bypass attempts
  2. Multi-Tenant Security

    • Cross-tenant data access attempts
    • SQL injection attempts (parameterized queries)
    • JSONB injection attempts
    • Path traversal attempts (Resource URIs)
  3. Input Validation

    • Tool parameter validation
    • Resource URI validation
    • JSON-RPC message validation
    • CSRF protection (HTTP transport)
  4. Sensitive Data Exposure

    • Log scrubbing (no API Keys, passwords logged)
    • Error messages (no stack traces to clients)
    • HTTPS enforcement (production)

Security Checklist:

  • OWASP Top 10 compliance
  • API Key BCrypt hashed (never plaintext)
  • HTTPS only (production)
  • Rate limiting enabled
  • CORS properly configured
  • SQL injection protected (EF Core parameterized)
  • XSS protection (JSON escaping)
  • Sensitive data not logged

Deliverables:

  • Security audit report (PASS/FAIL per category)
  • Vulnerability remediation plan (if issues found)

7.4 Bug Fixes & Refinement (1 day)

Bug Triage Process:

  1. Categorize bugs (CRITICAL, HIGH, MEDIUM, LOW)
  2. Fix CRITICAL and HIGH bugs immediately
  3. Defer MEDIUM/LOW bugs to backlog (if not blocking)

Expected Bug Types:

  • Integration test failures
  • Performance bottlenecks
  • Edge case handling (null values, empty lists)
  • Error message clarity

Deliverables:

  • Bug fix commits
  • Updated test suite (all passing)

Week 8: Documentation & Production Readiness

8.1 Architecture Documentation Update (2 days)

Documents to Update:

  1. MCP Server Architecture (docs/architecture/mcp-server-architecture.md)

    • Add SDK integration section (500+ lines)
    • Update component diagrams
    • Document hybrid architecture decisions
    • Add SDK vs. Custom comparison table
  2. SDK Migration Guide (docs/guides/mcp-sdk-migration.md) - NEW

    • Step-by-step migration instructions
    • Code examples (before/after)
    • Common pitfalls and solutions
    • Troubleshooting guide
  3. ADR: MCP SDK Adoption (docs/architecture/adr/005-mcp-sdk-adoption.md) - NEW

    • Decision context
    • Options considered
    • Decision rationale
    • Consequences and trade-offs

Deliverables:

  • 3 updated/new documents (1500+ lines total)
  • Architecture diagrams (Mermaid or Draw.io)
  • Code examples repository

8.2 API Documentation (1 day)

OpenAPI/Swagger Updates:

  1. Tool Endpoints

    • Document all 10 Tools
    • Parameter schemas
    • Response examples
    • Error codes
  2. Resource Endpoints

    • Document all 11 Resources
    • URI patterns
    • Query parameters
    • Response formats
  3. Authentication

    • API Key header format
    • Error responses (401, 403)
    • Rate limiting headers

Example Swagger Annotation:

[McpTool(Name = "create_issue")]
[SwaggerOperation(
    Summary = "Create a new issue",
    Description = "Creates Epic/Story/Task with Diff Preview approval workflow"
)]
[SwaggerResponse(200, "Pending change created", typeof(PendingChangeDto))]
[SwaggerResponse(400, "Invalid parameters")]
[SwaggerResponse(401, "Unauthorized")]
public class CreateIssueTool { ... }

Deliverables:

  • Complete Swagger/OpenAPI spec
  • Interactive API documentation (Swagger UI)

8.3 Code Cleanup (1 day)

Cleanup Tasks:

  1. Remove Old Code

    • Delete McpProtocolMiddleware.cs
    • Delete ApiKeyAuthMiddleware.cs
    • Delete IMcpTool.cs interface
    • Delete IMcpResource.cs interface
    • Remove obsolete NuGet packages
  2. Update Code Comments

    • Add XML documentation to public APIs
    • Update inline comments
    • Remove TODO/FIXME comments
  3. Code Style Enforcement

    • Run dotnet format
    • Fix StyleCop warnings
    • Consistent naming conventions
  4. Dependency Audit

    • Remove unused NuGet packages
    • Update vulnerable packages
    • Lock SDK version (avoid auto-updates)

Deliverables:

  • Clean codebase (zero warnings)
  • Updated .csproj files
  • Dependency lock file

8.4 Production Readiness & Deployment (2 days)

Production Readiness Checklist:

  • Testing

    • All integration tests pass (>80% coverage)
    • Performance benchmarks meet targets
    • Security audit passed (0 CRITICAL, 0 HIGH)
  • Documentation

    • Architecture docs updated
    • API docs complete
    • Migration guide published
  • Code Quality

    • Code reviewed and approved
    • Zero StyleCop warnings
    • No TODO/FIXME comments
  • Configuration

    • Environment variables documented
    • Secrets managed (Azure Key Vault / AWS Secrets Manager)
    • Feature flags configured
  • Deployment

    • Staging deployment successful
    • Smoke tests passed
    • Rollback plan documented

Staging Deployment:

  1. Deploy to staging environment
  2. Run smoke tests (5 critical scenarios)
  3. Monitor logs for errors
  4. Validate performance metrics

Smoke Test Scenarios:

  • Claude Desktop can connect (stdio)
  • Web client can connect (HTTP/SSE)
  • Create issue Tool works
  • List projects Resource works
  • Diff Preview approval flow works

Rollback Plan:

  • Database: No schema changes (safe to rollback)
  • Code: Git tag before deployment, revert if needed
  • Configuration: Feature flag to disable SDK (fallback to custom)

Deliverables:

  • Production readiness report (PASS/FAIL)
  • Staging deployment success confirmation
  • Rollback plan document

8.5 Final Code Review & Sign-Off (1 day)

Review Checklist:

  • Architect review (architecture compliance)
  • Tech lead review (code quality)
  • Security review (security best practices)
  • QA review (test coverage)
  • Product manager sign-off (business value delivered)

Sign-Off Criteria:

  • All acceptance criteria met (Epic level)
  • Performance targets achieved (≥20% improvement)
  • Security audit passed (0 CRITICAL, 0 HIGH)
  • Documentation complete
  • Production deployment plan approved

Deliverables:

  • Code review approval
  • Sign-off document (all stakeholders)

Acceptance Criteria

Testing

  • Integration test suite complete (50+ tests)
  • All integration tests pass (100%)
  • Performance benchmarks meet targets (≥20% improvement)
  • Security audit passed (0 CRITICAL, 0 HIGH)

Documentation

  • Architecture docs updated (1500+ lines)
  • API docs complete (Swagger)
  • Migration guide published
  • ADR documented

Code Quality

  • Old code removed (330+ lines)
  • Zero StyleCop warnings
  • XML documentation complete
  • Code reviewed and approved

Production Readiness

  • Staging deployment successful
  • Smoke tests passed
  • Rollback plan documented
  • All stakeholders signed off

Tasks Breakdown

Week 7: Testing & Optimization

  • Task 1 - End-to-end integration testing - 2 days
  • Task 2 - Performance testing and optimization - 2 days
  • Task 3 - Security audit - 1 day
  • Task 4 - Bug fixes and refinement - 1 day

Week 8: Documentation & Deployment

  • Task 5 - Architecture documentation update - 2 days
  • Task 6 - API documentation (Swagger) - 1 day
  • Task 7 - Code cleanup - 1 day
  • Task 8 - Production readiness and staging deployment - 2 days
  • Task 9 - Final code review and sign-off - 1 day

Progress: 0/9 tasks completed (0%)

Success Metrics

Quality Metrics

  • Test Coverage: ≥80%
  • Integration Tests: 50+ tests, 100% passing
  • Security: 0 CRITICAL, 0 HIGH vulnerabilities
  • Code Quality: 0 StyleCop warnings

Performance Metrics

  • Tool Execution: ≥20% faster (target: 120ms P95)
  • Resource Query: ≥30% faster (target: 85ms P95)
  • Throughput: ≥100 req/s (vs. 70 baseline)
  • Memory: ≤150 MB (vs. 180 baseline)

Documentation Metrics

  • Architecture Docs: 1500+ lines updated
  • API Docs: 100% Swagger coverage
  • Migration Guide: Complete step-by-step
  • Code Examples: 10+ before/after samples

Definition of Done

  • All Week 7 tasks complete (testing, optimization, security, bug fixes)
  • All Week 8 tasks complete (docs, cleanup, deployment, sign-off)
  • Integration tests pass (100%)
  • Performance targets met (≥20% improvement)
  • Security audit passed (0 CRITICAL, 0 HIGH)
  • Documentation complete (architecture, API, migration guide)
  • Code cleanup complete (old code removed, warnings fixed)
  • Staging deployment successful
  • Smoke tests passed
  • All stakeholders signed off

Created: 2025-11-09 by Product Manager Agent Owner: Backend Team Lead Start Date: 2026-01-06 (Week 7) Target Date: 2026-01-17 (End of Week 8) Status: Not Started