# ColaFlow Days 7-10 Roadmap
|
|
|
|
**Date**: 2025-11-03
|
|
**Prepared By**: Product Manager Agent
|
|
**Sprint**: M1 Sprint 2 - Enterprise-Grade Multi-Tenancy & SSO
|
|
**Status**: Planning Complete
|
|
|
|
---
|
|
|
|
## Overview
|
|
|
|
This roadmap outlines Days 7-10 of the 10-day sprint, building on the foundation established in Days 1-6 (Authentication, RBAC, Role Management).
|
|
|
|
**Strategic Goal**: Complete M1.1 core features and prepare for M2 MCP integration.
|
|
|
|
---
|
|
|
|
## Day 7: Email Service + Verification + Password Reset
|
|
|
|
**Duration**: 8 hours
|
|
**Priority**: P1 (High - Security and UX)
|
|
**Dependencies**: None (independent feature)
|
|
|
|
### Objectives
|
|
|
|
1. Integrate email service (SendGrid or SMTP)
|
|
2. Implement email verification flow
|
|
3. Implement password reset flow
|
|
4. Create email templates
|
|
5. Add rate limiting for security
|
|
|
|
### Deliverables
|
|
|
|
**Backend**:
|
|
- Email service abstraction (`IEmailService`)
|
|
- SendGrid implementation (primary)
|
|
- SMTP fallback implementation
|
|
- Email verification tokens (24-hour expiration)
|
|
- Password reset tokens (1-hour expiration)
|
|
- Rate limiting (max 5 verification emails/hour, max 3 reset emails/hour)
|
|
|
|
**API Endpoints**:
|
|
1. `POST /api/auth/verify-email` - Verify email with token
|
|
2. `POST /api/auth/resend-verification` - Resend verification email
|
|
3. `POST /api/auth/forgot-password` - Request password reset
|
|
4. `POST /api/auth/reset-password` - Reset password with token
|
|
|
|
**Database**:
|
|
- Add `email_verified` column to `identity.users`
|
|
- Add `email_verified_at` column
|
|
- Create `email_verification_tokens` table
|
|
- Create `password_reset_tokens` table
|
|
|
|
**Email Templates**:
|
|
- Welcome + verification email
|
|
- Password reset email
|
|
- Password changed confirmation email
|
|
|
|
**Tests**:
|
|
- 20+ integration tests
|
|
- Email delivery verification (use test inbox)
|
|
- Token expiration tests
|
|
- Rate limiting tests
|
|
|
|
### Success Criteria
|
|
|
|
- ✅ Emails sent successfully (99% delivery rate)
|
|
- ✅ Verification flow completes in < 30 seconds
|
|
- ✅ Password reset flow completes in < 30 seconds
|
|
- ✅ Rate limiting prevents abuse
|
|
- ✅ 100% test coverage
|
|
|
|
---
|
|
|
|
## Day 8: Project-Level Roles + Audit Logging
|
|
|
|
**Duration**: 8 hours
|
|
**Priority**: P0 (Critical - Required for M1 Projects module)
|
|
**Dependencies**: Day 6 (Role Management API)
|
|
|
|
### Objectives
|
|
|
|
1. Design and implement project-level role system
|
|
2. Implement role inheritance logic
|
|
3. Create authorization policies for project operations
|
|
4. Implement comprehensive audit logging
|
|
5. Prepare for M1.1 Projects CRUD
|
|
|
|
### Deliverables
|
|
|
|
**Domain Layer**:
|
|
- `ProjectRole` enum (ProjectOwner, ProjectManager, ProjectMember, ProjectGuest)
|
|
- `UserProjectRole` entity
|
|
- `IUserProjectRoleRepository` interface
|
|
- Role inheritance rules:
|
|
- TenantOwner → ProjectOwner (all projects)
|
|
- TenantAdmin → ProjectManager (all projects)
|
|
- Project-specific roles override tenant defaults
|
|
|
|
**Database**:
|
|
```sql
|
|
CREATE TABLE projects.user_project_roles (
|
|
id UUID PRIMARY KEY,
|
|
user_id UUID NOT NULL,
|
|
project_id UUID NOT NULL,
|
|
role VARCHAR(50) NOT NULL,
|
|
assigned_at TIMESTAMP NOT NULL,
|
|
assigned_by_user_id UUID NULL,
|
|
UNIQUE(user_id, project_id)
|
|
);
|
|
```
|
|
|
|
**Authorization Policies**:
|
|
- `RequireProjectOwner` - Full control over project
|
|
- `RequireProjectManager` - Manage tasks and team
|
|
- `RequireProjectMember` - Create and update tasks
|
|
- `RequireProjectAccess` - Read-only access
|
|
|
|
**Audit Logging**:
|
|
```sql
|
|
CREATE TABLE audit.audit_logs (
|
|
id UUID PRIMARY KEY,
|
|
tenant_id UUID NOT NULL,
|
|
user_id UUID NOT NULL,
|
|
action VARCHAR(100) NOT NULL,
|
|
entity_type VARCHAR(50) NOT NULL,
|
|
entity_id UUID NULL,
|
|
old_value JSONB NULL,
|
|
new_value JSONB NULL,
|
|
ip_address VARCHAR(50) NULL,
|
|
user_agent VARCHAR(500) NULL,
|
|
timestamp TIMESTAMP NOT NULL DEFAULT NOW()
|
|
);
|
|
```
|
|
|
|
**API Endpoints**:
|
|
1. `POST /api/projects/{projectId}/members` - Add member to project
|
|
2. `PUT /api/projects/{projectId}/members/{userId}/role` - Update member role
|
|
3. `DELETE /api/projects/{projectId}/members/{userId}` - Remove member
|
|
4. `GET /api/projects/{projectId}/members` - List project members
|
|
5. `GET /api/audit/logs` - Query audit logs (TenantOwner only)
|
|
|
|
**Tests**:
|
|
- 25+ integration tests
|
|
- Role inheritance tests
|
|
- Authorization policy tests
|
|
- Audit log verification
|
|
|
|
### Success Criteria
|
|
|
|
- ✅ Role inheritance works correctly
|
|
- ✅ All API operations logged
|
|
- ✅ Authorization policies enforce project-level permissions
|
|
- ✅ 100% test coverage
|
|
|
|
---
|
|
|
|
## Day 9: M1 Core Projects Module - Multi-Tenant Update
|
|
|
|
**Duration**: 8 hours
|
|
**Priority**: P0 (Critical - M1.1 core feature)
|
|
**Dependencies**: Day 8 (Project-level roles)
|
|
|
|
### Objectives
|
|
|
|
1. Update existing Projects module for multi-tenancy
|
|
2. Add project-level authorization
|
|
3. Integrate project roles
|
|
4. Complete Epics, Stories, Tasks multi-tenant update
|
|
5. Test full workflow (register → create project → manage tasks)
|
|
|
|
### Deliverables
|
|
|
|
**Database Migration**:
|
|
- Add `tenant_id` column to `projects.projects`
|
|
- Add `tenant_id` column to `projects.epics`
|
|
- Add `tenant_id` column to `projects.stories`
|
|
- Add `tenant_id` column to `projects.tasks`
|
|
- Update foreign keys
|
|
- Add EF Core global query filters
|
|
|
|
**Application Layer Updates**:
|
|
- Update all commands to include tenant context
|
|
- Add project role validation
|
|
- Update queries to filter by tenant
|
|
|
|
**API Updates**:
|
|
- Protect all endpoints with project-level authorization
|
|
- Example: `[Authorize(Policy = "RequireProjectMember")]`
|
|
- Add tenant validation middleware
|
|
|
|
**Tests**:
|
|
- 30+ integration tests
|
|
- Cross-tenant isolation tests
|
|
- Project role authorization tests
|
|
- Full workflow tests (E2E)
|
|
|
|
### Success Criteria
|
|
|
|
- ✅ All Projects/Epics/Stories/Tasks isolated by tenant
|
|
- ✅ Project-level authorization works
|
|
- ✅ No cross-tenant data leakage
|
|
- ✅ 100% test coverage
|
|
- ✅ Full E2E workflow passes
|
|
|
|
---
|
|
|
|
## Day 10: Kanban Workflow + Sprint Management
|
|
|
|
**Duration**: 8 hours
|
|
**Priority**: P1 (High - M1.1 core feature)
|
|
**Dependencies**: Day 9 (Projects module updated)
|
|
|
|
### Objectives
|
|
|
|
1. Implement Sprint management
|
|
2. Enhance Kanban board with sprint support
|
|
3. Add sprint burndown chart data
|
|
4. Implement sprint velocity tracking
|
|
5. Complete M1.1 core features
|
|
|
|
### Deliverables
|
|
|
|
**Domain Layer**:
|
|
- `Sprint` entity
|
|
- `SprintId` value object
|
|
- Sprint status (Planning, Active, Completed)
|
|
- Sprint business rules (start/end dates, task capacity)
|
|
|
|
**Database**:
|
|
```sql
|
|
CREATE TABLE projects.sprints (
|
|
id UUID PRIMARY KEY,
|
|
project_id UUID NOT NULL,
|
|
tenant_id UUID NOT NULL,
|
|
name VARCHAR(100) NOT NULL,
|
|
goal TEXT NULL,
|
|
start_date DATE NOT NULL,
|
|
end_date DATE NOT NULL,
|
|
status VARCHAR(20) NOT NULL,
|
|
created_at TIMESTAMP NOT NULL,
|
|
FOREIGN KEY (project_id) REFERENCES projects.projects(id)
|
|
);
|
|
|
|
ALTER TABLE projects.tasks
|
|
ADD COLUMN sprint_id UUID NULL,
|
|
ADD CONSTRAINT fk_tasks_sprints FOREIGN KEY (sprint_id) REFERENCES projects.sprints(id);
|
|
```
|
|
|
|
**API Endpoints**:
|
|
1. `POST /api/projects/{projectId}/sprints` - Create sprint
|
|
2. `PUT /api/projects/{projectId}/sprints/{sprintId}` - Update sprint
|
|
3. `DELETE /api/projects/{projectId}/sprints/{sprintId}` - Delete sprint
|
|
4. `POST /api/projects/{projectId}/sprints/{sprintId}/start` - Start sprint
|
|
5. `POST /api/projects/{projectId}/sprints/{sprintId}/complete` - Complete sprint
|
|
6. `GET /api/projects/{projectId}/sprints` - List sprints
|
|
7. `GET /api/projects/{projectId}/sprints/{sprintId}/burndown` - Burndown data
|
|
8. `POST /api/projects/{projectId}/tasks/{taskId}/assign-to-sprint` - Add task to sprint
|
|
|
|
**Analytics**:
|
|
- Sprint burndown chart data (remaining story points per day)
|
|
- Sprint velocity (completed story points per sprint)
|
|
- Sprint completion percentage
|
|
- Team capacity utilization
|
|
|
|
**Tests**:
|
|
- 20+ integration tests
|
|
- Sprint workflow tests
|
|
- Burndown calculation tests
|
|
- Velocity tracking tests
|
|
|
|
### Success Criteria
|
|
|
|
- ✅ Full sprint lifecycle works (create → start → complete)
|
|
- ✅ Tasks can be assigned to sprints
|
|
- ✅ Burndown chart data accurate
|
|
- ✅ Velocity tracking functional
|
|
- ✅ 100% test coverage
|
|
- ✅ **M1.1 COMPLETE**
|
|
|
|
---
|
|
|
|
## Summary Timeline
|
|
|
|
| Day | Feature | Priority | Hours | Dependencies | Risk |
|
|
|-----|---------|----------|-------|--------------|------|
|
|
| **6** | Role Management API | P0 | 6-8 | Day 5 RBAC | LOW |
|
|
| **7** | Email Service + Verification + Password Reset | P1 | 8 | None | MEDIUM |
|
|
| **8** | Project-Level Roles + Audit Logging | P0 | 8 | Day 6 | MEDIUM |
|
|
| **9** | Projects Multi-Tenant Update | P0 | 8 | Day 8 | MEDIUM |
|
|
| **10** | Kanban Workflow + Sprint Management | P1 | 8 | Day 9 | LOW |
|
|
|
|
**Total Days**: 5 days (Days 6-10)
|
|
**Total Hours**: 38-40 hours
|
|
**Critical Path**: Day 6 → Day 8 → Day 9 → Day 10
|
|
|
|
---
|
|
|
|
## Milestone Completion Status
|
|
|
|
### M1.1 - Core Project Module (Days 1-10)
|
|
|
|
**Progress**: 83% → 100% (after Day 10)
|
|
|
|
**Completed** (Days 1-5):
|
|
- ✅ Domain layer (Projects, Epics, Stories, Tasks)
|
|
- ✅ Infrastructure layer (EF Core, PostgreSQL)
|
|
- ✅ Application layer (CQRS commands/queries)
|
|
- ✅ API layer (RESTful endpoints)
|
|
- ✅ Unit tests (96.98% coverage)
|
|
- ✅ JWT authentication
|
|
- ✅ Refresh token mechanism
|
|
- ✅ RBAC system (5 tenant roles)
|
|
|
|
**Remaining** (Days 6-10):
|
|
- [ ] Role Management API (Day 6)
|
|
- [ ] Email verification (Day 7)
|
|
- [ ] Project-level roles (Day 8)
|
|
- [ ] Multi-tenant Projects update (Day 9)
|
|
- [ ] Sprint management (Day 10)
|
|
|
|
**After Day 10**:
|
|
- ✅ M1.1 **100% COMPLETE**
|
|
- ✅ Ready for M1.2 (SSO Integration)
|
|
- ✅ Ready for M2 (MCP Server)
|
|
|
|
---
|
|
|
|
## Days 11-12: M2 MCP Server Foundation (Optional Extension)
|
|
|
|
**Duration**: 16 hours (2 days)
|
|
**Priority**: P0 (Critical for M2 milestone)
|
|
**Dependencies**: Days 6-10 complete
|
|
|
|
### Objectives
|
|
|
|
1. Design MCP authentication architecture
|
|
2. Implement MCP token generation
|
|
3. Create preview and approval workflow
|
|
4. Implement basic MCP resources
|
|
5. Implement basic MCP tools
|
|
|
|
### High-Level Deliverables
|
|
|
|
**MCP Authentication**:
|
|
- MCP token format: `mcp_<tenant_slug>_<random_32_chars>`
|
|
- Token scopes: read, create, update, delete, execute
|
|
- Token expiration: 90 days (configurable)
|
|
- Token revocation
|
|
|
|
**Database**:
|
|
```sql
|
|
CREATE TABLE identity.mcp_tokens (
|
|
id UUID PRIMARY KEY,
|
|
tenant_id UUID NOT NULL,
|
|
token_hash VARCHAR(500) NOT NULL UNIQUE,
|
|
name VARCHAR(100) NOT NULL,
|
|
scopes JSONB NOT NULL,
|
|
expires_at TIMESTAMP NOT NULL,
|
|
created_by_user_id UUID NOT NULL,
|
|
created_at TIMESTAMP NOT NULL,
|
|
last_used_at TIMESTAMP NULL
|
|
);
|
|
```
|
|
|
|
**Preview System**:
|
|
```sql
|
|
CREATE TABLE mcp.previews (
|
|
id UUID PRIMARY KEY,
|
|
tenant_id UUID NOT NULL,
|
|
mcp_token_id UUID NOT NULL,
|
|
operation VARCHAR(100) NOT NULL,
|
|
entity_type VARCHAR(50) NOT NULL,
|
|
entity_id UUID NULL,
|
|
diff JSONB NOT NULL,
|
|
status VARCHAR(20) NOT NULL, -- Pending, Approved, Rejected
|
|
created_at TIMESTAMP NOT NULL,
|
|
reviewed_by_user_id UUID NULL,
|
|
reviewed_at TIMESTAMP NULL
|
|
);
|
|
```
|
|
|
|
**MCP Resources** (Read-only):
|
|
- `projects.search` - Search projects
|
|
- `projects.get` - Get project details
|
|
- `tasks.list` - List tasks
|
|
- `tasks.get` - Get task details
|
|
- `reports.daily` - Daily progress report
|
|
|
|
**MCP Tools** (Write with preview):
|
|
- `create_task` - Create task (requires approval)
|
|
- `update_task_status` - Update task status (requires approval)
|
|
- `add_comment` - Add comment to task (auto-approved)
|
|
- `assign_task` - Assign task to user (requires approval)
|
|
|
|
**API Endpoints**:
|
|
1. `POST /api/mcp/tokens` - Generate MCP token
|
|
2. `GET /api/mcp/tokens` - List tokens
|
|
3. `DELETE /api/mcp/tokens/{tokenId}` - Revoke token
|
|
4. `POST /api/mcp/preview` - Create preview for approval
|
|
5. `POST /api/mcp/preview/{previewId}/approve` - Approve preview
|
|
6. `POST /api/mcp/preview/{previewId}/reject` - Reject preview
|
|
7. `GET /api/mcp/resources/{resourceId}` - MCP resource endpoint
|
|
8. `POST /api/mcp/tools/{toolName}` - MCP tool endpoint
|
|
|
|
**Tests**:
|
|
- 40+ integration tests
|
|
- MCP authentication tests
|
|
- Preview workflow tests
|
|
- Resource access tests
|
|
- Tool execution tests
|
|
|
|
### Success Criteria
|
|
|
|
- ✅ MCP tokens generated and validated
|
|
- ✅ Preview workflow works (create → approve/reject → execute)
|
|
- ✅ All MCP resources accessible
|
|
- ✅ All MCP tools functional
|
|
- ✅ 100% test coverage
|
|
- ✅ **M2.1 Foundation COMPLETE**
|
|
|
|
---
|
|
|
|
## Risk Management
|
|
|
|
### High-Risk Items
|
|
|
|
| Risk | Impact | Probability | Mitigation |
|
|
|------|--------|-------------|------------|
|
|
| Day 8 complexity (project roles) | HIGH | MEDIUM | Start simple, iterate later |
|
|
| Email service delays (Day 7) | MEDIUM | MEDIUM | Use SMTP fallback |
|
|
| Scope creep (Days 11-12) | HIGH | HIGH | Strictly time-box, defer to Sprint 3 |
|
|
| Cross-tenant bugs (Day 9) | HIGH | LOW | Comprehensive integration tests |
|
|
|
|
### Mitigation Strategies
|
|
|
|
1. **Daily check-ins**: Review progress at end of each day
|
|
2. **Time-boxing**: Strictly limit each day to 8 hours
|
|
3. **Test-first approach**: Write tests before implementation
|
|
4. **Code reviews**: Backend agent reviews all code
|
|
5. **Incremental delivery**: Deploy after each day
|
|
|
|
---
|
|
|
|
## Success Metrics
|
|
|
|
### Sprint Success Criteria (Days 6-10)
|
|
|
|
- ✅ All deliverables completed on time
|
|
- ✅ Zero critical bugs in production
|
|
- ✅ 100% test coverage maintained
|
|
- ✅ M1.1 milestone 100% complete
|
|
- ✅ Ready for M2 MCP integration
|
|
|
|
### Quality Metrics
|
|
|
|
- **Test Coverage**: ≥ 85% (current: 96.98%)
|
|
- **API Response Time**: < 200ms (p95)
|
|
- **Bug Density**: ≤ 0.5 bugs per feature
|
|
- **Code Quality**: No SonarQube violations
|
|
- **Documentation**: 100% API endpoints documented
|
|
|
|
### Business Metrics
|
|
|
|
- **Feature Completion Rate**: 100% (no deferred features)
|
|
- **Development Velocity**: 5 features in 5 days
|
|
- **Time to Market**: M1.1 completed in 10 days (on schedule)
|
|
- **Customer Value**: Complete authentication + authorization + role management
|
|
|
|
---
|
|
|
|
## Recommendations
|
|
|
|
### Immediate Actions (Day 6)
|
|
|
|
1. ✅ Approve Day 6 planning document
|
|
2. ✅ Assign Role Management API to backend agent
|
|
3. ✅ Begin implementation (6-8 hours)
|
|
4. ✅ Deploy to development environment
|
|
|
|
### Medium-Term Actions (Days 7-10)
|
|
|
|
1. Review and approve each day's plan before starting
|
|
2. Daily progress check-ins
|
|
3. Continuous integration testing
|
|
4. Code reviews after each feature
|
|
|
|
### Long-Term Actions (M2)
|
|
|
|
1. Plan M2 MCP integration (16-hour sprint)
|
|
2. Design AI agent interaction patterns
|
|
3. Implement preview and approval workflow
|
|
4. Test ChatGPT/Claude integration
|
|
|
|
---
|
|
|
|
## Alternative Scenarios
|
|
|
|
### Scenario 1: Days 11-12 Deferred
|
|
|
|
**If** scope exceeds 10 days:
|
|
- **Action**: Defer MCP foundation to Sprint 3
|
|
- **Impact**: Delays M2 milestone by 1-2 weeks
|
|
- **Mitigation**: Focus on M1.1 completion first
|
|
|
|
### Scenario 2: Email Service Issues (Day 7)
|
|
|
|
**If** SendGrid integration fails:
|
|
- **Action**: Use SMTP fallback (Gmail or local SMTP)
|
|
- **Impact**: Slower email delivery, no analytics
|
|
- **Mitigation**: Implement SendGrid in Sprint 3
|
|
|
|
### Scenario 3: Project Roles Too Complex (Day 8)
|
|
|
|
**If** role inheritance exceeds 8 hours:
|
|
- **Action**: Simplify to basic project roles (no inheritance)
|
|
- **Impact**: TenantOwner must be explicitly added to projects
|
|
- **Mitigation**: Add inheritance in Sprint 3
|
|
|
|
---
|
|
|
|
## Conclusion
|
|
|
|
**Days 7-10 Roadmap**: Comprehensive plan to complete M1.1 milestone
|
|
|
|
**Key Milestones**:
|
|
- Day 7: Email infrastructure
|
|
- Day 8: Project-level authorization
|
|
- Day 9: Multi-tenant Projects
|
|
- Day 10: Sprint management
|
|
- **M1.1 100% COMPLETE**
|
|
|
|
**Next Sprint** (M1.2 - Optional):
|
|
- Days 11-12: MCP Server foundation
|
|
- M2 milestone kickoff
|
|
|
|
**Strategic Value**:
|
|
- Complete authentication/authorization stack
|
|
- Enable multi-tenant SaaS operations
|
|
- Prepare for AI/MCP integration
|
|
- Deliver enterprise-grade features
|
|
|
|
---
|
|
|
|
**Document Status**: ✅ Planning Complete - Ready for Execution
|
|
|
|
**Prepared By**: Product Manager Agent
|
|
**Date**: 2025-11-03
|
|
**Version**: 1.0
|